KaitaiaWhangareiDargavilleAucklandThamesTaurangaHamiltonWhakataneRotoruaTokoroaTe KuitiTaumarunuiTaupoGisborneNew PlymouthNapierHastingsDannevirkeWhanganuiPalmerston NorthLevinParaparaumuMastertonWellingtonMotuekaNelsonBlenheimWestportReeftonKaikouraGreymouthHokitikaChristchurchAshburtonTimaruWanakaOamaruQueenstownDunedinGoreInvercargill
NZ HeraldThe Northern AdvocateThe Northland AgeThe AucklanderWaikato HeraldBay Of Plenty TimesRotorua Daily PostHawke's Bay TodayWhanganui ChronicleThe Stratford PressManawatu GuardianKapiti NewsHorowhenua ChronicleTe Awamutu CourierVivaEat WellOneRoofDRIVEN Car GuideThe CountryPhoto SalesiHeart RadioRestaurant Hub
Voyager 2023 media awards
Subscribe
Advertisement
Advertise with NZME.
Home / Business

Auckland's multi-billion data centre boom: DCI ups its spend to $600m with second server farm

Chris Keall
By
Chris Keall
21 Jan, 2022 04:00 PM6 mins to read
Saveshare

Share this article

Reminder, this is a Premium article and requires a subscription to read.

facebookcopy linktwitterlinkedinredditemail
Image / Getty Creative

Image / Getty Creative

Auckland's multibillion-dollar data centre boom just got bigger, with Australian contender DCI Data Centres revealing that it now plans to spend $600 million on two new facilities.

The pandemic has accelerated a boom in cloud computing, or using software and services over the internet - from the likes of Zoom and Slack to Netflix and multiplayer games.

While "the cloud" is often used as a metaphor, online services and online storage involve giant data centres or "server farms" filled with thousands or tens of thousands of computers, all of which need to be cooled.

Keeping data centres local is better for performance, and means that the likes of banks and government departments don't have to worry about the data sovereignty issues that can complicate life if files are stored in server farms overseas, where different privacy and security laws can apply.

New Zealand currently has no data centres in the top-tier "hyperscale" class.

But suddenly, many are on the way. In May 2020, half Infratil-owned Canberra Data Centres (CDC) announced plans for two hyperscale data centres: a 7000sqm facility in Hobsonville and an 11,000sq m server farm in Silverdale in a $300m-plus project that now has construction underway.

Microsoft soon followed, breaking ground in February 2021 on the first of three hyperscale data centres in northwest Auckland. The tech giant has not put a price tag on the project, other than to confirm that it is something more than the $100m threshold for Overseas Investment Office approval. Early customers will include Fonterra, BNZ and Spark.

In August, Spark said it would upgrade its Takanini data centre to a 10 megawatt hyperscale facility in a project that would - at least for a while - be New Zealand's largest server farm (in the complex cloud wars, Spark co-operates with the multinationals for some services, and uses its in-house infrastructure for others).

Advertisement
Advertise with NZME.

And Amazon has said it will spend $7.5 billion building a cluster of huge data centres in Auckland, due to open in 2024 as it creates a local Amazon Web Services (AWS) region.

Tim Dacombe-Bird, the New Zealand head of AWS, said company's $7.5b figure included the cost of building at least three data centres and stocking them with hardware, plus operating costs including utilities and salaries. Dacombe-Bird said the Amazon's build would create 1000 new jobs.

Related articles

Business

Microsoft reveals details of three giant data centres for Auckland

10 Feb 07:58 PM
Business

CDS plans $300m data centres for Hobsonville, Silverdale

21 Oct 04:57 AM
Business

After broadband miss, Spark doubles down on 5G spend

18 Aug 05:30 AM
Business

$700m data centre for Southland: Backers welcome Tiwai turnaround

14 Jan 12:41 AM

His company claims the build will have a $10.4b positive economic impact on this country's economy over its first decade.

And now we have the latest development: DCI's purchase of a five-hectare (or 50,000sqm) site on the North Shore - where CEO Malcolm Roe says it will build NZ's largest server farm, which will be known as "AKL02".

The Australian firm already has a giant data centre under construction at Westgate, AKL01, which is due to open in 2023.

An artist's impression of "AKL02", which will be build on Auckland's North Shore. Image / Supplied
An artist's impression of "AKL02", which will be build on Auckland's North Shore. Image / Supplied

Construction on AKL02 - which the Herald understands is in the Albany/Rosedale area - will begin in the middle of this year, with commercial operation due to begin in 2024.

It's no coincidence that the new wave of supermassive data centres will be clustered around the North Shore and the nearby northwest, given that international cables land at Takapuna and Whenuapai, while Albany houses NZ's largest internet peering exchange - or facility to help internet traffic get to the right place, in the fastest possible time.

Roe says DCI's combined data centre build will involve $600m in direct construction and setup costs.

Advertisement
Advertise with NZME.

"AKL01 and AKL02 will have a combined economic value exceeding $1.4b over the life of the projects. Each data centre will create more than 150 jobs during construction and approximately 250 ongoing skilled information technology and telecommunications jobs once the sites are operational," Roe says.

DCI Data Centers chief executive Malcolm Roe (left) with Auckland Deputy Mayor Bill Cashmore. Photo / Supplied
DCI Data Centers chief executive Malcolm Roe (left) with Auckland Deputy Mayor Bill Cashmore. Photo / Supplied

Data centres are described by the amount of power they require at peak operation.

Roe says AKL02 will be a 40 megawatt facility - which, as things stand, would make it NZ's largest data centre (AKL01 will be a 10MW server farm).

The DCI boss says his company is already in talks with Vector about the "power design" for his company's North Shore facility.

"Window dressing"

He says that will involve a pledge to use 100 per cent renewable power - by which he means hydro and geothermal generated electricity.

Many server farms offshore feature banks of solar panels, but Roe says the technology is not practical for the Auckland builds.

"Even if we covered the whole 5 hectares in solar panels, that would only generate a tenth of the power required by AKL02," he says. "Lots of the solar panels you see on data centres are just window dressing."

Roe adds that his company is working on new sustainability solutions with Naylor Love, which won the contract to build AKL01 at Westgate (AKL02 is still out to tender).

"DCI is leading the industry in delivering new cooling technologies to significantly enhance our power utilisation effectiveness and water utilisation effectiveness to minimise our impact on the environment," says Roe.

Data centre commercial politics will be another factor, once all the new facilities come online.

Microsoft partners closely with CDC across the Tasman. And while it is based in Sydney, DCI is owned by Canada's Brookfield Asset Management - the company that teamed with Infratil to buy Vodafone NZ.

Southland contender?

The intertwined field could become more crowded yet.

Startup Datagrid - whose backers include rich-lister Malcolm Dick and Singapore's BW Group - is planning a $530m, 60MW hyperscale facility in Southland.

The plan, first revealed in 2020, sees Datagrid taking up some of the slack from Meridian's 572MW Manapouri Power Station after the Tiwai smelter is taken offline.

The scheme depends on funding being found for a new international fibre cable that would link Invercargill, Dunedin and Christchurch with Los Angeles, Singapore and Jakarta - which would become the South Island's first major broadband link with the outside world.

The cable would be operated by Hawaiki Cable, which was founded by Dick and others and bought by BW Group for an undisclosed sum last year. Hawaiki already operates a trans-Pacific Cable with landing points in Auckland and Northland.

While funds are still being rustled up, Datagrid announced in the New Year that it has bought a 43-hectare site in North Makarewa, a rural area about 20km north of Invercargill.

All going to plan, Datagrid will open the first phase of its planned data centre in 2024 as a 60MW facility, with a plan to upgrade it to 100MW.

Famine to feast - and a little too much feast

With Auckland about to go from no hyperscale data centres to at least 10 (three built by Microsoft, at least three from Amazon, two from CDC and DCI's twin set), is the market big enough for that many players?

"New Zealand is underserved for public cloud infrastructure," says Roe.

All the data centres announced or under construction for Auckland (and NZ, excluding the drawing-board Datagrid) total about 80MW, by the DCI boss' estimate - a big boost on today but still well short of the 450MW of data centres clustered around Sydney.

"So there's still room for massive grow," he says.

Saveshare

Share this article

Reminder, this is a Premium article and requires a subscription to read.

facebookcopy linktwitterlinkedinredditemail
Advertisement
Advertise with NZME.

Latest from Business

Premium
Business

The remarkable David Lomas: TV star opens up on reuniting families, love and surviving a fatal air crash with Paul Holmes

10 Dec 06:13 AM
Premium
Business

Opinion: Central banks and the return of the unreliable boyfriend

10 Dec 05:00 AM
Premium
Business

Debt hangover? More Kiwis plan to put Christmas on the plastic

10 Dec 02:00 AM
Premium
Business

Global pre-Christmas trade at risk due to twin canal crises

10 Dec 01:29 AM

More houses coming

sponsored
Advertisement
Advertise with NZME.

Latest from Business

Premium
The remarkable David Lomas: TV star opens up on reuniting families, love and surviving a fatal air crash with Paul Holmes

The remarkable David Lomas: TV star opens up on reuniting families, love and surviving a fatal air crash with Paul Holmes

10 Dec 06:13 AM

How a top investigative journalist has created some of TV's most emotional moments.

Premium
Opinion: Central banks and the return of the unreliable boyfriend

Opinion: Central banks and the return of the unreliable boyfriend

10 Dec 05:00 AM
Premium
Debt hangover? More Kiwis plan to put Christmas on the plastic

Debt hangover? More Kiwis plan to put Christmas on the plastic

10 Dec 02:00 AM
Premium
Global pre-Christmas trade at risk due to twin canal crises

Global pre-Christmas trade at risk due to twin canal crises

10 Dec 01:29 AM
Kiwi’s business dream a global winner
sponsored

Kiwi’s business dream a global winner

About NZMEHelp & SupportContact UsSubscribe to NZ HeraldHouse Rules
Manage Your Print SubscriptionNZ Herald E-EditionAdvertise with NZMEBook Your AdPrivacy Policy
Terms of UseCompetition Terms & ConditionsSubscriptions Terms & Conditions
© Copyright 2023 NZME Publishing Limited
TOP