Lovatt said it had discussed with contractor Downer the importance of working around the clock if necessary to get the job done as quickly as possible.
''We want to make sure that 24-hour work is done on key parts of the project where we don't have a situation where there's a construction site impinging their journey without any progress.''
Roadworks near the airport in late 2016 led to traffic chaos and in some cases passengers and crew being late for planes although finished work since then has eased congestion.
Lovatt said there would be frequent advice to airport users on how to avoid disruption.
The widened George Bolt Drive would have more provision for bus lanes, however, plans released this morning don't have details of light rail which has been part of a government plan for the airport.
Lovatt said the airport was working with government agencies on rail but plans for light rail had not ''bottomed out yet.''
Rail corridors leading to a terminus near the airport terminal had been set aside.
He said the ''Northern Network' road project was one of eight key anchor projects planned for over the next decade. Others include a second runway and an integrated domestic and international terminal.
Included is a three-lane one way loop road through a pick up/drop off zone at the international terminal before connecting back into George Bolt Memorial Drive.
Passenger numbers are expected to more than double to 40 million a year by 2044. It has been forecast the number of vehicle trips to and from the airport will increase to more than 127,000 per day in 2044.