"The line removal will cause a brief traffic delay while the reinstatement of new wire might disrupt the flow for 10-15 minutes. Our contractors are well prepared to minimise any interruptions and there will be considerable traffic management in place."
New poles will be installed on either side of the railway line and Kiwi Rail representatives will be on site on Monday to alert crews of any train movements.
Powerco has three contractors, Obertech, Linepower and Downer, engaged for the York Rd work which will involve six planned power shut downs spread over two weeks, says Ian.
"These have been scheduled to cause the least disruption and we appreciate the co-operation of the residents there."