From March 3 to March 5 stop/stop will be needed between Barrett Rd and Te Karaka Drive.
During this time there will be a one-hour traffic hold with a 10-minute traffic release to allow 60m sections to be milled and resurfaced.
On March 6 to 7 and March 10, traffic control will revert to stop/go.
There will be no works on March 8 and March 9.
Temporary speed limits will be in place during the day due to the worksite having a different level to the normal road, with ramps transitioning traffic between the sites, where required.
The announcement comes after angry motorists last month lashed out at lengthy traffic delays on the state highway, one commuter describing the situation as an “absolute joke”.