However, the regional council stated the Rena consent application had been particularly complex, with:
•23 technical reports submitted with the application,
•151 submissions received in response to the application
•An independent hearing panel established to hear, consider and decide on the application
•The hearing took 20 days. Lists and transcripts of all submitters, technical advisors, expert witnesses, and information presented at the hearing is available on www.renaresourceconsent.org.nz
The panel has released a 450-page document which outlines the conditions of the monitoring of the wreckage.
The Rena salvage cost more than $500 million. Crews recovered 1107 containers and 1467 cubic metres of oil from Rena.
Regional council chief executive Mary-Anne Macleod said the consent application had been granted subject to an 'extensive suite of conditions' outlined within a 451 page document.
Ms Macleod said under section 120 of the Rescource Management Act, any person who made a submission now had 15 days to reappeal the decision to the Environment Court.