By spring 2019, this section of Albert St will be reinstated with a new road surface, bus lanes, widened footpaths and street furniture.
CRL project director Chris Meale says the start of bulk excavation is another milestone for the project.
Cut-and-cover construction is being used at each end of the CRL tunnels - between Britomart Station and the future Aotea Station on Albert St and, later, where it connects to the western line at Mt Eden. Between Aotea and Mt Eden stations, the tunnels will be between 13m and 42m below ground and bored using a 7m diameter tunnel-boring machine.
The first stage of the project, from Britomart to the Wyndham St intersection with Albert St, represents about 10 per cent of the 3.4km twin underground tunnels between Britomart and Mt Eden.
For more information, visit https://www.cityraillink.co.nz/crl-cut-cover-tunnel-excavation/