The carrying value of the North Island grid upgrade land portfolio was further impaired, by $19.7m, bringing the total impairment on the upgrade property to $49.7m.
That reflected the reduction of the value of property bought in Waikato and South Auckland, most in 2006 and 2007, to enable construction of the new line. The fall in value was due to a general fall in land values in the region, Transpower said.
Depreciation and amortisation increased by $21m, including a $9m adjustment to asset depreciation following a review of asset lives. The remainder of the increase was due to increased asset capitalisation through Transpower's build programme.
Operating costs rose $15m, including a $6m increase in planned maintenance.
Mr Verbiest said Transpower's two largest projects - the North Island grid upgrade and Pole 3 of the HVDC link - were well advanced. Construction also started recently on a new underground cable through Auckland's CBD and to the north, called the North Auckland and Northland project.
Together, those three large grid projects would cost nearly $2 billion.
They were part of an overall capital programme, expected to be around $5b over the next 10 years, that would significantly increase the capacity, performance and resilience of the grid.
Equally important was significant ongoing investment in replacing and refurbishing older equipment.
- NZPA