"The journey took 3 hours to complete and it's a credit to all those involved in the months of planning and organisation that it went so smoothly given the size of the load," said tunnel construction manager, Chris Ashton.
Once at the ports, the main drive and the other largest part of the boring machine were packed up and shipped back to the manufacturer, Herrenknecht's main factory in Germany.
Starting in November 2013, Alice bored 4.8km from Waterview to Alan Wood Reserve, Owairaka, to create the country's longest road tunnels, each twice the length of the Auckland Harbour Bridge. The three-lane traffic tunnels each way to connect the Southwestern and Northwestern motorways along Auckland's 48km Western Ring Route between Manukau and Albany.
Well-Connected Alliance produced a video about Alice's heart making its final journey to the ports.