Albert-Eden Local Board chairman Peter Haynes said when the project was announced that the board backed intensification but "two major arterial roads meet almost at the front door", he said, referring to Manukau Rd and Green Lane West Rd.
"What would be the impact on traffic flows that are already problematic? Is the developer going to contribute to improvements at the intersection, for example?" he asked in 2014.
"Parking is also an issue, especially since the proposed development is on the site of a carpark that gets good use when large events are happening at the race track or the ASB Showgrounds," Haynes said at the time.
Canam Construction won the contract to build the places and its managing director Loukas Petrou said about 30,000 cubic metres of earth and about 2500 cubic metres of basalt rock had been removed from the site.
"With the removal of the rock, we've been crushing it on site so it can be used as backfill behind retaining walls and under the basement slabs," he said.