The lifts have the second largest design capacity in the world, rated to carry up to for 11.2 tonnes each and objects up to 3m long, SkyCity said.
More than 20 conferences have been confirmed and there are more than 250 in the conference, meeting or convention sales pipeline.
The project by Fletcher Construction is on a 1.4ha site, will be 32,500sqm of floor space or the equivalent of 3.2ha of indoor floorspace, five times larger than the existing New Zealand convention areas.
The property will be able to host conferences and one-off events for up to 4000 people and will have New Zealand's largest theatre.
At the new five-star Horizon Hotel, electrical, plumbing, communication, security and air conditioning work is underway from the basement through to the sixth level.
The concrete floors are poured up to the top or level 12 of the hotel and steel works are being installed for the roof.
Yet, when Fletcher won the contract in October 2015, construction was predicted to start in late December that year, run for 38 months and that would give it a potential finish date in February next year.
SkyCity is withholding $26.9 million from the Fletcher Construction Company because of issues.
In notes to the annual accounts contained in the annual report released to the NZX, SkyCity reveals that the $26.9m is liquidated damages and kept "as it considers that it has the right to these funds under the liquidated damages provisions in the construction contract with FCC."
Fletcher has notified SkyCity "that they dispute SkyCity's right to these liquidated damages," the accounts say.
The money was due to be paid to Fletcher under the progress claim as the NZICC rises but issues with the job resulted in SkyCity penalising its builder.
The centre is not now due to open until next December.