But the port only has rights to transfer and dump up to 400,000 cubic metres of dredged material to a dump site near Cuvier Island - limited in total to 2 million cubic metres over the next 34 years.
'Worst cast scenario'
A port spokesperson said the estimate represents a "worst case scenario" of the amount of dredging required. "The last time POAL undertook capital dredging, in the early 2000s, the company applied to remove 1 million cubic metres but in the end only needed to remove 600,000 cubic metres."
He told BusinessDesk that the volume of dredged material will not impact the first stage of the programme, only stage two, "which is some years away."
"The port will ensure that there is a legal disposal option in place before stage two commences, either via the designated disposal site or via an authorised alternative disposal option."
Iwi group Ngati Whatua Orakei said there was a serious cultural issue relating to the origin of the dredge material and plans to dump it in another rohe.
Ngarimu Blair, deputy chair of Ngati Whatua Orakei, said the proposed transfer of 2.5 million cubic metres of spoil from his iwi's rohe and "dumping it in the rohe of other iwi, in particular Ngati Wai and Ngati Rehua ki Aotea, without their consent, is deeply offensive to the tikanga of Ngati Whatua Orakei."
Blair said while a consent for dumping of dredge material already existed, the activity must be considered as a whole, and that the proposed dredging activity "would entirely account for, and exceed, the quantum consented at Cuvier."
The Ngati Whatua Orakei submission said that dumping of spoil will also have "significant adverse effects on the receiving environment, including despoiling of kai moana (seafood) and the "high risk of the introduction of contaminants and invasive non-indigenous species."