The new Hastings to Havelock North water main is one of the major steps in a comprehensive water strategy with a raft of improvements made to the district's water infrastructure. The objective of the strategy is to supply water that is safe and of sufficient quantity to meet demand, now and into the future. That includes closing down the Brookvale bore field in Havelock North.
The new 4.5km pipe will follow a path from Sylvan Rd to St Aubyn St, along Howard St to Georges Rd, then along Crosses Rd to Havelock North where it will be attached to the existing Karanema Dr water main. A new booster pump station will be built to improve supply to upper areas of Havelock North.
HDC's tenders subcommittee can now approve tenders for the project up to a combined value of $8.5 million. The mains and pump station project is expected to cost just under $10m.
The project will involve multiple contracts as the range of required skills and expertise will not be available from one company. Having contractors working on a number of fronts means that work can progress as fast as possible, Kevin says.