The Country
  • The Country home
  • Latest news
  • Audio & podcasts
  • Opinion
  • Dairy farming
  • Sheep & beef farming
  • Rural business
  • Rural technology
  • Rural life
  • Listen on iHeart radio

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • Coast & Country News
  • Opinion
  • Dairy farming
  • Sheep & beef farming
  • Horticulture
  • Animal health
  • Rural business
  • Rural technology
  • Rural life

Media

  • Podcasts
  • Video

Weather

  • Kaitaia
  • Whāngarei
  • Dargaville
  • Auckland
  • Thames
  • Tauranga
  • Hamilton
  • Whakatāne
  • Rotorua
  • Tokoroa
  • Te Kuiti
  • Taumurunui
  • Taupō
  • Gisborne
  • New Plymouth
  • Napier
  • Hastings
  • Dannevirke
  • Whanganui
  • Palmerston North
  • Levin
  • Paraparaumu
  • Masterton
  • Wellington
  • Motueka
  • Nelson
  • Blenheim
  • Westport
  • Reefton
  • Kaikōura
  • Greymouth
  • Hokitika
  • Christchurch
  • Ashburton
  • Timaru
  • Wānaka
  • Oamaru
  • Queenstown
  • Dunedin
  • Gore
  • Invercargill

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / The Country

SH25A to re-open by end of March 2024, says Waka Kotahi

Jim Birchall
By Jim Birchall
Former editor - HC Post·Hauraki Coromandel Post·
26 Jun, 2023 09:57 PM3 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

Proof drilling is carried out to check the depth of rock at pile locations at the SH25A site.

Proof drilling is carried out to check the depth of rock at pile locations at the SH25A site.

Physical works are under way for the construction of a bridge reconnecting State Highway 25A in the Coromandel, to be completed by the end of March, said Waka Kotahi New Zealand Transport Agency in a release today.

The beleaguered road has been closed since January 27, when cracks appeared. Further damage followed in the form of a significant slip brought on by excess rainfall that washed away part of the highway near the summit a few kilometres from Kōpu.

Waka Kotahi announced on May 9 that the project to build a bridge to replace the area of missing road would start in June.

In a release, Waka Kotahi says there are no delays in getting started on the project, which is expected to cost $30 million to $40m.

“While contract negotiations with the preferred consortia are ongoing, there has been no delay to the work programme,” said Jo Wilton, Waka Kotahi NZ Transport Agency regional manager of infrastructure delivery for the Waikato/Bay of Plenty.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

“A bridge of this type would normally be expected to take 12 to 14 months to construct, but Waka Kotahi is working with the consortia to accelerate delivery and get the route open in nine months’ time, by the end of March 2024,” said Wilton.

“A small, private dawn blessing took place at the site this morning signalling the formal start of enabling works,” said the release.

A blessing with Ngāti Maru kaumātua took place on Tuesday, enabling works to begin on the SH25a construction site. Photo / Supplied
A blessing with Ngāti Maru kaumātua took place on Tuesday, enabling works to begin on the SH25a construction site. Photo / Supplied

“Drainage water management is under way today, with earthworks to build all-weather access tracks for heavy machinery the next job ahead,” said Wilton.

Advertisement
Advertise with NZME.

During the past fortnight, project ecologists and the design and construction team have been visiting the site to confirm design assumptions and develop construction methodologies.

Artist’s impression of the bridge design showing the location of the cranes. Photo / Supplied
Artist’s impression of the bridge design showing the location of the cranes. Photo / Supplied

“Drilling to confirm the founding depth of the piles at the location of the bridge abutments began last Wednesday under the jurisdiction of Waka Kotahi contractors who remained in charge of the site until the consortium were given the keys following the blessing this morning,” said Wilton.

“Waka Kotahi is doing everything possible to further accelerate construction, which will include contractors working extended hours at the work site and working seven days a week where possible.

An aerial view of State Highway 25A, which was washed out near the summit during heavy rain on the Coromandel Peninsula at the end of January.
An aerial view of State Highway 25A, which was washed out near the summit during heavy rain on the Coromandel Peninsula at the end of January.

“Up to 100 people will be working at the SH25A Taparahi site, with additional labour dedicated to off-site works, such as prefabrication of bridge components.

“Workers will be divided into two teams working two 10-hour shifts, with 80 per cent of the crew housed locally on the peninsula,” said Wilton.

Over the next two months, a platform will be built to support the cranes required for the build.

Pile casings will be in the country by the end of July, with piling getting under way in August.

Save

    Share this article

Latest from The Country

Premium
Analysis

‘Ardern lives in exile’: Jones attacks gas ban, calls for apology in fiery hearing

19 Jun 05:00 AM
The Country

The Country: Hello Brendan, goodbye Rowena

19 Jun 01:47 AM
The Country

Huinga dairy farmer celebrated at national sustainability awards

18 Jun 10:37 PM

Jono and Ben brew up a tea-fuelled adventure in Sri Lanka

sponsored
Advertisement
Advertise with NZME.

Latest from The Country

Premium
‘Ardern lives in exile’: Jones attacks gas ban, calls for apology in fiery hearing

‘Ardern lives in exile’: Jones attacks gas ban, calls for apology in fiery hearing

19 Jun 05:00 AM

The Resources Minister came to the select committee sporting a Make NZ Great Again hat.

The Country: Hello Brendan, goodbye Rowena

The Country: Hello Brendan, goodbye Rowena

19 Jun 01:47 AM
Huinga dairy farmer celebrated at national sustainability awards

Huinga dairy farmer celebrated at national sustainability awards

18 Jun 10:37 PM
'Technology has come so far': Drones could be coming to farms and beaches near you

'Technology has come so far': Drones could be coming to farms and beaches near you

18 Jun 06:00 PM
Help for those helping hardest-hit
sponsored

Help for those helping hardest-hit

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • NZ Herald e-editions
  • Daily puzzles & quizzes
  • Manage your digital subscription
  • Manage your print subscription
  • Subscribe to the NZ Herald newspaper
  • Subscribe to Herald Premium
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Bay of Plenty Times
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • NZME Events
  • © Copyright 2025 NZME Publishing Limited
TOP