Hastings Mayor Sandra Hazlehurst recently said the council is acutely aware of how important it is for communities to have access restored, and some of the work has been costing peaks of as much as $600,000 a day.
“There is a huge programme of work being undertaken to have our network repaired and rebuilt, and it’s been great to see the bridges and crossings that have been installed to date,” she said.
“There is a lot more to do, but we are working as quickly as we can – our thanks go to all the teams involved in pulling out the stops to get this done, and to our communities for their patience.”
The demolition of the broken sections of Redclyffe Bridge was “going well, with three-four weeks remaining”, the council said, adding it was working with the adjacent community through options for a temporary solution which could coincide with demolition.
“The earliest potential date for opening is the end of June,” it said in a media release.
A solution for the Brookfield Bridge, between Meeanee and Pākōwhai, was among other bridge options being investigated.
Some of the works done so far: a Bailey bridge has been installed to replace the Rissington Bridge, a temporary bridge has been put in place at Dartmoor, the Ellis-Wallace low-level crossing has been installed in Esk Valley, the Arapaoanui low-level crossing has opened and temporary access has been established for Matapiro Bridge.
Bailey bridges are planned for the Ellis-Wallace, Moeangiangi and Mangatutu low-level crossings, and unless there are unexpected disruptions, it is estimated they will open at the end of this month.
A Bailey bridge at Whanawhana could be open next Monday, the day national highways management agency Waka Kotahi New Zealand Transport Agency plans to re-open State Highway 2′s Napier-Wairoa route, with a Bailey bridge now in place at the site of the Waikare Bridge which was destroyed, near Putorino.
The design of the Crystal Twin culvert is complete and temporary access has been reinstated for this structure, as well as the McVicars culvert. Crownthorpe Bridge is due to be complete at the end of June, and solutions for the Darkeys Spur No. 1, Puketapu and Kereru Rd Gorge bridges are also being investigated.