The site included areas of 4700ha and 600ha, to be connected by a transmission corridor.
As well as wind turbines and solar arrays, there would be a battery energy storage system, a permanent meteorological mast and an internal substation, the application said.
“The project will create a substantial number of additional jobs during the construction period, with an estimated 450 to 550 direct full-time equivalent jobs required.
“The economic benefit from additional employment in the area will continue during operations with up to 20 direct full-time equivalent jobs for the lifetime of the project.”
The project was one of the largest economic renewable energy development opportunities in New Zealand “that Meridian is aware of”, and would produce enough electricity to power 290,000 homes.
If given the green light, construction would start in March 2027, with “full power” by June 2032.
South Taranaki Mayor Phil Nixon says the project is exciting but he and his council need more information. Photo / NZME
Meridian’s head of renewable development, Rebecca Knott, told the Whanganui Chronicle an indication of final costs would not be known until detailed designs were complete.
In August, Meridian will begin building the $227 million Ruakākā Solar Farm in Northland, with 230GWh to be produced each year from 250,000 solar panels.
That will be the company’s first New Zealand solar farm.
Its $448m Harapaki Wind Farm project in Hawke’s Bay, which features 41 wind turbines, became fully operational last July and can produce enough electricity to power 70,000 average homes.
Meridian's Harapaki Wind Farm in Hawke's Bay has 41 wind turbines.
Guerin’s application said Meridian began engaging the relevant iwi authority, Te Kaahui o Rauru (TKoR), about the project in 2022, and it was “committed to engaging experts within TKoR at the appropriate stage of development”.
Knott said next month’s open day was a chance for the public to better understand the project, ask questions and provide feedback.
“If it goes ahead, we’ll be part of the community for a long time and we want to start building those connections,” she said.
“We’re currently undertaking technical assessments, working through the design process and engaging with iwi and the wider community.”
Meridian would make an updated application to the Government’s fast-track approvals process in the next few months, she said.
If that was successful, it would need to submit a substantive application to be considered by an independent expert panel.
“For a large project like the Waiinu Energy Park, the fast-track process may not actually end up being much faster.
“The more important thing for us is that it provides certainty about the steps we need to take to gain approval to build the project.”
Mike Tweed is a multimedia journalist at the Whanganui Chronicle. Since starting in March 2020, he has dabbled in everything from sport to music. At present his focus is local government, primarily the Whanganui District Council.