Sections of pipe are being welded into strings up to 450m long and stored along the side of Memorial Park. This welding work is continuing into the evenings. Noise from the welding work is minimal and super silent generators are being used, the council said in a statement.
Once the harbour drilling was completed, the welded steel pipes would be winched through to Matapihi from Memorial Park. Polyethylene wastewater pipe would then be pushed through inside the steel casing. The steel casing would provide a protective layer between the wastewater pipe and the soils deep under the harbour.
The entire project is scheduled to be completed in December 2017. Both construction sites at Matapihi and Memorial Park will be returned to their original states once the project is finished.
More information about the Southern Pipeline
The $21 million harbour crossing is the final stage of the $99 million Southern Pipeline project, one of several key infrastructure projects being built to cater for the rapid growth being seen in Tauranga.
The pipeline will relieve pressure from the Chapel Street Wastewater Treatment Plant by redirecting much of the city's wastewater to the treatment plant at Te Maunga, which has extra capacity.
It will connect the wastewater network between Memorial Park and Matapihi through a pipeline deep beneath the harbour bed, at a depth of up to 35m.
Southern Pipeline construction started in started in 2009. The harbour crossing construction began in February 2017. The entire Southern Pipeline project is due to be completed and functioning at the end of the year.