NZ HeraldThe Northern AdvocateThe Northland AgeThe AucklanderWaikato HeraldBay Of Plenty TimesRotorua Daily PostHawke's Bay TodayWhanganui ChronicleThe Stratford PressManawatu GuardianKapiti NewsHorowhenua ChronicleTe Awamutu CourierVivaEat WellOneRoofDriven MotoringThe CountryPhoto SalesNZ Herald InsightsWatchMeGrabOneiHeart RadioRestaurant Hub

Advertisement

Advertise with NZME.
Whanganui Chronicle

South Taranaki Waipipi Wind Farm parts arrive from China

26 May, 2020 05:00 PM2 minutes to read
A turbine foundation is poured at Waipipi Wind Farm. Photo / Paul Brooks

A turbine foundation is poured at Waipipi Wind Farm. Photo / Paul Brooks

Laurel Stowell
By
Laurel Stowell

Reporter

VIEW PROFILE

Turbine parts for the Waipipi Wind Farm in South Taranaki have arrived in New Zealand.

The first Chinese ship carrying towers and blades arrived in Port Taranaki on May 21, about 10 days ahead of schedule, project manager Jim Pearson said. They will now be trucked to the 980ha site, which is on the coast between Waverley and Patea.

Construction of the 31-turbine wind farm began in October last year. It's a $227 million project of renewable energy generator Tilt Renewables.

Work stopped completely and there was only security on site during the level 4 lockdown. It resumed under level 3, with contractors working in bubbles and vehicles digitally tracked after entry.

Advertisement

Advertise with NZME.

The dry summer has speeded progress, Pearson said. A compound has been set up as base for the 80 to 90 workers on site, and most of the 18km of internal roads have been made.

The wind farm has a central compound with offices and toilets. Photo / Paul Brooks
The wind farm has a central compound with offices and toilets. Photo / Paul Brooks

A concrete batching plant is pouring the 430 cubic metres of concrete needed for each turbine foundation. The 12th foundation was being poured yesterday .

Before they are poured, the sandy soil is "improved" to fortify it against liquefaction or sideways movement during earthquakes.

READ MORE:
• Waverley's Waipipi Wind Farm construction starts with turning of first sod
• Pre-construction under way for South Taranaki wind farm
• Tilt Renewables board to proceed with South Taranaki wind farm
• Premium - Waverley Wind farm boss optimistic about future

The main contractor for construction is Higgins, and Electrotronet is handling the electrical side. It involves an underground electrical cable network, connecting the turbines, and 11km of overhead transmission lines taking electricity to the Waverley Substation.

Most of the poles for that line are already in, Pearson said, and are visible from Waverley's Fookes and Swinburne Streets. Some residents were so concerned about them that they were thinking of fighting the wind farm consent, but did not proceed.

Related articles

$276 million wind farm with 'largest ever' rotor diameter

03 Sep 12:31 AM

Waipipi Iron Sands reunion 30 years on

03 Oct 03:26 AM

International turnout to see first sod turned at wind farm

05 Nov 04:00 PM

First electricity from Waipipi Wind Farm by October

14 Feb 04:00 PM

There has been no public reaction to the poles and transmission line, Pearson said.

Work to erect the wind turbines will begin from the end of June, and numbers on site are expected to rise to 150 to 160.

Advertisement

Advertise with NZME.

The wind farm may begin generating electricity in October. Its total output is projected to be 955GWh per year, enough to power 70,000 homes and save the emission of 350,000 tonnes of carbon.

Premium gold

Advertisement

Advertise with NZME.

Latest from Whanganui Chronicle

Whanganui Chronicle

Warm, wet and windy weather expected

17 Aug 02:30 AM
Whanganui Chronicle

Whanganui records 60 new Covid-19 cases

17 Aug 01:20 AM
Whanganui Chronicle

Graeme Storm exhibition on now at Quartz Museum of Studio Ceramics

17 Aug 12:45 AM
Whanganui Chronicle

Cubs and keas converge on council

17 Aug 12:35 AM
Premium
Whanganui Chronicle

Theatre group reassured over landslide repairs

16 Aug 05:00 PM

Most Popular

Premium
Whitebaiting season drops from 15 weeks to nine, concerns spots could be crowded
Whanganui Chronicle

Whitebaiting season drops from 15 weeks to nine, concerns spots could be crowded

15 Aug 05:00 PM
Tariana Turia's grandson attempted to rob service station
Whanganui Chronicle

Tariana Turia's grandson attempted to rob service station

11 Aug 05:00 PM
Premium
'It's like a grater on raw wounds': Mum, 35, says mesh implant cripples her
Whanganui Chronicle

'It's like a grater on raw wounds': Mum, 35, says mesh implant cripples her

09 Aug 05:00 PM

Advertisement

Advertise with NZME.
About NZMEHelp & SupportContact UsSubscribe to Whanganui ChronicleHouse Rules
Manage Your Print SubscriptionWhanganui Chronicle E-EditionAdvertise with NZMEBook Your AdPrivacy Policy
Terms of UseCompetition Terms & ConditionsSubscriptions Terms & Conditions
© Copyright 2022 NZME Publishing Limited
TOP