Bay of Plenty Times
  • Bay of Plenty Times home
  • Latest news
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Sport
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Business
  • Opinion
  • Lifestyle
  • Property
    • All Property
    • Residential property listings
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology
  • Sport

Locations

  • Coromandel & Hauraki
  • Katikati
  • Tauranga
  • Mount Maunganui
  • Pāpāmoa
  • Te Puke
  • Whakatāne
  • Rotorua

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Thames
  • Tauranga
  • Whakatāne
  • Rotorua

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • What the Actual
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / Bay of Plenty Times

Tauranga council projects delayed amid LTP deliberations, three waters blamed

Kiri Gillespie
By Kiri Gillespie
Assistant News Director and Multimedia Journalist·Bay of Plenty Times·
4 Mar, 2024 11:43 PM3 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

Mount Maunganui and Tauranga CBD as seen from above. Key Mount projects have been delayed due to budget constraints. Photo / Mead Norton

Mount Maunganui and Tauranga CBD as seen from above. Key Mount projects have been delayed due to budget constraints. Photo / Mead Norton

Major projects aimed at helping Tauranga cope with a rapidly growing population could be pushed back due to “budget limitations”.

A statement released last nightsaid while deliberating the Long-term Plan 2024-34 Tauranga City Council commissioners had to “alter priorities” around key investment projects.

Transport and roading plans for Mount Maunganui and Ōtūmoetai had now been delayed, as had the completion of Cameron Rd Stage Two works.

The council began deliberations on the plan, which includes significant projects such as a proposed community stadium, Te Manawataki o Te Papa updates, and Te Tumu, yesterday.

As part of those deliberations, the commission opted to scrap a controversial road-pricing project.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

The coalition Government’s repeal of the Water Services Acts meant the council needed to provide planned investment in water services from year three of the long-term plan onwards, pushing some projects out.

In the statement, commission chairwoman Anne Tolley said changes were required to the timing of major projectsdue to the additional three waters capital required.

The council commission had to take into account how many infrastructure projects the city could cope with at any one time and spread the delivery phases.

Advertisement
Advertise with NZME.

“Since taking on our roles, we have been playing catch-up on years [of] underinvestment in the city, however, we are also mindful the city has a threshold for disruption linked to infrastructure projects. What we’ve tried to do here is create a balance, so that the city doesn’t fall further behind, but that key works are staggered,” Tolley said.

“The Ōtūmoetai and Mount multi-modal projects have been moved towards the end of the LTP period.”

The Accessible Streets for Ōtūmoetai and Mount Maunganui projects aims to provide safer and easier access for people in Matua, Bureta, Cherrywood, Ōtūmoetai, Bellevue, Judea and Mount Maunganui walking, cycling or bus-riding. A business case for Ōtūmoetai was approved in December 2023 and this was yet to be reviewed.

Works to improve transport corridors on Hewletts Rd, Aerodrome Rd and Totara St were also unlikely to progress in the immediate future.

“This reflects revised prioritisation indications from the Government for NZTA [Waka Kotahi NZ Transport Agency] subsidy,” Tolley said.

“However, tackling Tauranga’s congestion issues is more important than ever, so the Turret Rd/15th Ave project which could really ease pressure in that part of town, has been moved to earlier in the LTP.”

The Turret Rd/15th Ave project aims to create a third tidal lane between Burrows St and the SH29A/Maungatapu intersection to help alleviate congestion.

Tolley said costs of the second stage of the Cameron Rd upgrade project had increased, meaning its completion date was now 2030 instead of 2028 at the time of the draft long-term plan.

“This considers some planning uncertainties yet to be resolved.”

A review of the Cameron Road upgrade was labelled a failure for not addressing the financial losses businesses suffered as a direct result of the council-led project.

Advertisement
Advertise with NZME.

Yesterday, the council agreed to a residential rates increase from the draft long-term plan and created a new “rating category” to help make the system fairer, Tolley said.

A new industrial general rate meant residential rates were about 3 per cent lower than they would have been, she said.

The Long-term Plan 2024-34 has residential rates estimated to increase by 8.3 to 9.4 per cent (including an estimated IFF levy) but final rates are expected to be published with the plan is adopted in April.


Save

    Share this article

Latest from Bay of Plenty Times

Bay of Plenty Times

'Major step': New 24/7 urgent care for Tauranga by 2026

18 May 02:08 AM
Bay of Plenty Times

Luxon announces $164m for new 24/7 urgent care services

18 May 01:22 AM
Bay of Plenty Times

How NZ beaches inspired UK author's debut novel

18 May 12:00 AM

The Hire A Hubby hero turning handyman stereotypes on their head

sponsored
Advertisement
Advertise with NZME.

Latest from Bay of Plenty Times

'Major step': New 24/7 urgent care for Tauranga by 2026

'Major step': New 24/7 urgent care for Tauranga by 2026

18 May 02:08 AM

Papamoa's after-hours clinic closed in November due to financial challenges.

Luxon announces $164m for new 24/7 urgent care services

Luxon announces $164m for new 24/7 urgent care services

18 May 01:22 AM
How NZ beaches inspired UK author's debut novel

How NZ beaches inspired UK author's debut novel

18 May 12:00 AM
Severe weather warnings: 120km/h gales, thunderstorms possible

Severe weather warnings: 120km/h gales, thunderstorms possible

17 May 11:18 PM
Gold demand soars amid global turmoil
sponsored

Gold demand soars amid global turmoil

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Bay of Plenty Times e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Bay of Plenty Times
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Bay of Plenty Times
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • What the Actual
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven CarGuide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • NZME Events
  • © Copyright 2025 NZME Publishing Limited
TOP