Rotorua Daily Post
  • Rotorua Daily Post home
  • Latest news
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Sport
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Business
  • Opinion
  • Lifestyle
    • All Lifestyle
    • Residential property listings
  • Property
    • All Property
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology
  • Rural
  • Sport

Locations

  • Tauranga
  • Te Puke
  • Whakatāne
  • Rotorua
  • Tokoroa
  • Taupō & Tūrangi

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales

Weather

  • Rotorua
  • Tauranga
  • Whakatāne
  • Tokoroa
  • Taupō

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • What the Actual
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / Rotorua Daily Post

State Highway 1 Tīrau to Waiōuru accelerated maintenance project reaches halfway point

Maryana Garcia
By Maryana Garcia
Multimedia Journalist·Waikato Herald·
23 Apr, 2025 04:32 AM4 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

The State Highway 1 Tīrau to Waiōuru accelerated maintenance project aimed to complete four years’ worth of road renewals in 16 months.

The State Highway 1 Tīrau to Waiōuru accelerated maintenance project aimed to complete four years’ worth of road renewals in 16 months.

Announced last August, the State Highway 1 Tīrau to Waiōuru accelerated maintenance project aimed to complete four years’ worth of road renewals in 16 months.

As the project reaches its halfway point, Transport Minister Chris Bishop said in a statement that 119 lane kilometres of SH1 had been rehabilitated or resealed.

“As this huge maintenance effort comes to an end, I want to thank the truckies, motorists, and local residents who’ve been so patient through the necessary traffic disruptions.”

Bishop also thanked NZ Transport Agency Waka Kotahi (NZTA) contractors “who worked hard to improve big sections of New Zealand’s most important road”.

“These were some pretty sad sections of state highway which had needed an astonishing 5670 pothole repairs over the previous couple of years.”

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.
Transport Minister Chris Bishop. Photo / Tom Eley
Transport Minister Chris Bishop. Photo / Tom Eley

Bishop said making so many short-term repairs was inefficient.

The accelerated programme saw some sections of the highway being completely rebuilt.

“The Tīrau to Waiōuru project is part of the Government’s $2.07 billion Pothole Prevention fund and condenses four years of roadworks into two road maintenance seasons.”

Advertisement
Advertise with NZME.

Bishop said drivers would notice improvements from the maintenance, drainage, road rebuilding and safety work “immediately”.

“These upgrades mean the road is more forgiving if someone makes a mistake, with crashes less likely to result in death or serious injury.”

At the programme's peak, 145 truckloads of roading metal were being delivered every day across the closed sections of SH1.
At the programme's peak, 145 truckloads of roading metal were being delivered every day across the closed sections of SH1.

According to Bishop, 32 contracting firms have worked over 110,000 hours to get this far.

“At the project’s peak, 145 truckloads of roading metal were being delivered every day across the closed sections of state highway.”

The second half will begin in September.

“There is still a lot of work to do,” Bishop said.

“This includes the final surfacing on the sections worked on this season, and more maintenance and road rebuilding between Taupō to Tūrangi, and in the Tīrau and Tokoroa townships.

“However, the work between Taupō to Tūrangi will not involve a full 24/7 road closure and the final surfacing work will be done under stop/go and or at night.”

National Road Carriers commercial transport specialist Paula Rogers.
National Road Carriers commercial transport specialist Paula Rogers.

National Road Carriers Association commercial transport specialist Paula Rogers said feedback from operators has been positive.

“The transport sector understands the complexity of these major projects and has accepted the closures, knowing that they help speed up the work.

Advertisement
Advertise with NZME.

“Our roads need to be fit for purpose, and if short-term closures are necessary to get the job done efficiently, we adapt and work around them.

“Communication throughout these projects has been clear and concise, which has made alternative route planning much easier for our sector.”

The second season of the accelerated roadworks programme will begin in September.
The second season of the accelerated roadworks programme will begin in September.

NZTA regional transport systems manager Sandra King said the agency was “very pleased” with the amount of work contractors had completed.

“We haven’t just carried out much needed road maintenance work, we’ve also completely rebuilt the road in some areas.

“If we had done this work under traditional stop/go traffic management it could have taken up to four years to complete.”

King said NZTA was aware of the inconveniences and challenges caused by road closures.

Advertisement
Advertise with NZME.

“We’re incredibly thankful for everyone’s patience and understanding as we worked.”

King said the programme for next season “is being worked on”.

“NZTA will be speaking to communities, businesses, and freight when we have more details to share.”

The SH1 Tīrau to Waiōuru project by the numbers:

  • 119 lane km (601,000m2) completed, including:
  • 198,366 Tonnes of aggregate used;
  • Up to 145 truckloads of metal per day delivered across all closures;
  • 110,000 roadcrew hours to date;
  • Zero time lost due to injuries;
  • 32 contracting firms on the go at once.

Maryana Garcia is a Hamilton-based reporter covering breaking news in Waikato. She previously wrote for the Rotorua Daily Post and Bay of Plenty Times.

Save

    Share this article

Latest from Rotorua Daily Post

Rotorua Daily Post

'Drop-kick losers': Outrage as masked gang of trail bikers tear up kids' rugby fields

16 May 06:36 AM
Rotorua Daily Post

Entertainment figure takes name suppression case to Supreme Court

16 May 05:00 AM
Rotorua Daily Post

Fourth time's the charm: Pound puppy finds forever home

16 May 02:00 AM

The Hire A Hubby hero turning handyman stereotypes on their head

sponsored
Advertisement
Advertise with NZME.

Latest from Rotorua Daily Post

'Drop-kick losers': Outrage as masked gang of trail bikers tear up kids' rugby fields

'Drop-kick losers': Outrage as masked gang of trail bikers tear up kids' rugby fields

16 May 06:36 AM

Parents and coaches confronted masked bikers at Rotorua rugby fields.

Entertainment figure takes name suppression case to Supreme Court

Entertainment figure takes name suppression case to Supreme Court

16 May 05:00 AM
Fourth time's the charm: Pound puppy finds forever home

Fourth time's the charm: Pound puppy finds forever home

16 May 02:00 AM
Premium
Glimmer of hope for Chateau Tongariro restoration as former lessee accounts for $5m provision

Glimmer of hope for Chateau Tongariro restoration as former lessee accounts for $5m provision

16 May 01:00 AM
Gold demand soars amid global turmoil
sponsored

Gold demand soars amid global turmoil

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Rotorua Daily Post e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Rotorua Daily Post
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Rotorua Daily Post
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Bay of Plenty Times
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • What the Actual
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven CarGuide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • NZME Events
  • © Copyright 2025 NZME Publishing Limited
TOP