Hawkes Bay Today
  • Hawke's Bay Today home
  • Latest news
  • Sport
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Sport
  • Business
  • Opinion
  • Lifestyle
  • Property
    • All Property
    • Residential property listings
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology

Locations

  • Napier
  • Hastings
  • Havelock North
  • Central Hawke's Bay
  • Tararua

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Napier
  • Hastings
  • Dannevirke
  • Gisborne

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In

Advertisement
Advertise with NZME.
Home / Hawkes Bay Today

Work to start on another rural Hawke’s Bay bridge destroyed in Cyclone Gabrielle

Michaela Gower
Michaela Gower
Multimedia Journalist·Hawkes Bay Today·
20 Jan, 2026 03:00 AM3 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save
    Share this article
Construction on the Dartmoor Bridge in Hawke's Bay is due to start on February 2. Photo / Michaela Gower

Construction on the Dartmoor Bridge in Hawke's Bay is due to start on February 2. Photo / Michaela Gower

A date has been set for construction to begin on the Dartmoor Bridge, almost three years after it was destroyed in Cyclone Gabrielle.

The Dartmoor Rd bridge over the Mangaone River suffered a complete loss of all five bridge piers and seven spans during the February 2023 cyclone.

A pedestrian bridge was installed at the end of March that year, followed by a temporary single-lane bridge on April 5 that is still in use.

Hastings District Council programme delivery manager David Scrimgeour said construction would begin on the new structure on February 2 and the rebuild would have minimal impact on road users and residents.

The new bridge will be built immediately downstream from the temporary structure and will be 104m in length with four spans.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

Scrimgeour said it would be rebuilt with a single lane because of low traffic volumes, but wide enough for modern farm equipment to safely traverse it, and high productivity motor vehicles (HPMV) loading.

“The temporary structure will remain open throughout construction of the permanent bridge.”

Scrimgeour said the rebuild of the bridge was expected to be finished in late 2026 and was expected to cost $13m, all of which is 100% Government funded through National Infrastructure Funding and Financing.

Advertisement
Advertise with NZME.
Pier piling is complete, with the installation of abutments underway at the Rissington Bridge. Photo / Hastings District Council
Pier piling is complete, with the installation of abutments underway at the Rissington Bridge. Photo / Hastings District Council

Meanwhile, Scrimgeour said the Rissington bridge rebuild was progressing as planned and is on track to be completed by September 2026.

“The pier piling is complete, with the installation of abutments underway; pier column reinforcing is being and has been installed in preparation for concrete pouring.”

Scrimgeour said the precast headstocks, which sit on top of the pier columns, will be installed in late February, and beam installation is expected to begin late March or early April.

“Ahead of tree felling needed for site access, bats were recorded during acoustic monitoring, which required ecologist input to manage removal, in line with Resource Consent conditions.

“Additional testing was required for the ground improvement verification (densification of soft soils using rammed aggregate stone columns).”

Scrimgeour said Follies Bridge on Waihau Rd is currently in detailed design, with construction planned to start following the completion of Dartmoor Bridge.

Construction is expected to take about nine months, and the design will inform the construction cost.

“Dartmoor has slightly more challenges than Rissington Bridge due to the need for deeper foundation piles and larger temporary works footprint as access is more constrained,” Scrimgeour said.

“Those are well understood by Fulton Hogan following the early contractor involvement phase, which helped shape the final design prior to contract award.”

Michaela Gower joined Hawke’s Bay Today in 2023 and is based out of the Hastings newsroom. She covers Dannevirke and Hawke’s Bay news and loves sharing stories about farming and rural communities.

Advertisement
Advertise with NZME.
Save
    Share this article

Latest from Hawkes Bay Today

Hawkes Bay Today

Mount Maunganui landslide: Recovery of six missing could take weeks

26 Jan 06:27 AM
Hawkes Bay Today

Ever-reliable Robson helps Hawke’s Bay to title, but may miss Hawke Cup clash

26 Jan 04:02 AM
Hawkes Bay Today

Hastings Cornwall Park theft: Stolen turtles slowly make their way home

26 Jan 04:00 AM

Sponsored

Discover Australia with AAT Kings’ easy-going guided holidays 

15 Jan 12:33 AM
Advertisement
Advertise with NZME.

Latest from Hawkes Bay Today

Mount Maunganui landslide: Recovery of six missing could take weeks
Hawkes Bay Today

Mount Maunganui landslide: Recovery of six missing could take weeks

Police say the recovery could last many days and possibly extend to weeks.

26 Jan 06:27 AM
Ever-reliable Robson helps Hawke’s Bay to title, but may miss Hawke Cup clash
Hawkes Bay Today

Ever-reliable Robson helps Hawke’s Bay to title, but may miss Hawke Cup clash

26 Jan 04:02 AM
Hastings Cornwall Park  theft: Stolen turtles slowly make their way home
Hawkes Bay Today

Hastings Cornwall Park theft: Stolen turtles slowly make their way home

26 Jan 04:00 AM


Discover Australia with AAT Kings’ easy-going guided holidays 
Sponsored

Discover Australia with AAT Kings’ easy-going guided holidays 

15 Jan 12:33 AM
NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Hawke's Bay Today e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Hawke's Bay Today
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Hawke's Bay Today
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Bay of Plenty Times
  • Rotorua Daily Post
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • NZME Events
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • © Copyright 2026 NZME Publishing Limited
TOP