The update said the significant consent risks and stakeholder concerns had put this major project behind schedule, with the capital budget of $300,000 for the 2018/19 year significantly underspent because the scope of consenting had changed due to discussions with the CRG.
“A consent will no longer be lodged at this stage, and will depend on further consultation and direction from councillors.”
The budget for the year would, however, still be spent, as the focus would now be on engineering design, site investigations and planning matters that were required regardless of consent processes.
Another risk noted was escalation of construction costs, to which the council said: “The project team has a very strong focus on delivery of the most cost-effective upgrade solution. The aim is to save costs wherever possible to reduce this risk. Furthermore, external experts have been contracted to investigate key aspects of the upgrade proposal (eg solids disposal) with the intention of finding innovative means to reduce costs.”