Whanganui Chronicle
  • Whanganui Chronicle home
  • Latest news
  • Sport
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Sport
  • Business
  • Opinion
  • Lifestyle
  • Property
    • All Property
    • Residential property listings
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology

Locations

  • Taranaki
  • National Park
  • Whakapapa
  • Ohakune
  • Raetihi
  • Taihape
  • Marton
  • Feilding
  • Palmerston North

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • New Plymouth
  • Whanganui
  • Palmertson North
  • Levin

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / Whanganui Chronicle

Showdown with engineers over plant's design

By John Maslin
Whanganui Chronicle·
11 Dec, 2014 05:27 PM4 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

SETBACK: Reviews of the wastewater plant suggest it may be too expensive to run.

SETBACK: Reviews of the wastewater plant suggest it may be too expensive to run.

A meeting in Wellington today will hopefully explain why a peer review of Wanganui's planned wastewater treatment plant upgrade is at odds with the new design.

In a surprise setback for the district council's wastewater plant project, the reviewers have said they cannot rely on earlier estimates of the amount of sludge that will be "digested" in the primary pond. On their estimates, the volume of sludge could make the plant unaffordable.

Cardno BTO designed the new plant at Airport Rd and it was peer-reviewed by AECOM and CH2Beca, both of which have told council they cannot rely on those initial estimates and both have predicted sludge quantities would increase.

Russell Bell, appointed project manager in September, said he and council senior wastewater engineer Arno Benadie would "eyeball" Cardno representatives in the capital this afternoon.

"We need to understand why there are differences," Mr Bell said.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

"What you've got is two engineers with different opinions.

"We have to determine if the issue with the sludge might sit somewhere in the middle."

Solutions could include adding more mechanical kit to the design to speed up the digestion process to reduce the solids in the pond.

Advertisement
Advertise with NZME.

"There have been a number of things suggested but we need to understand whether that will get the sludge down to a level we want," Mr Bell said.

He said the information Cardno gave council in June looked good financially in terms of the quantity of sludge and associated costs.

"But the peer review has seen the sludge quantity go up considerably - and information we're getting from landfill operators at Bonny Glen is that their prices have gone up as well. So we've got two increases working in tandem.

"We need to verify that and come back to council."

Mr Bell said Cardno had used Beach Rd as the basis for its calculations on waste volumes going into the treatment plant.

"They put that information into their model as assumptions of what loads will be and then added in the peak loads created in summer. Out of that, they calculated the by-products going on the pond and one of those is sludge."

The next step was testing the assumptions Cardno had made in its design.

He said the key was operational costs and they needed to narrow costs down so council knew what ongoing costs would be.

"Sludge is an issue for all plants but there are mechanisms used around the world which could reduce the sludge or at least manage it."

Mayor Annette Main said they needed to sort out why there was a difference of opinion.

Advertisement
Advertise with NZME.

"What makes one side think the pond is going to digest and what makes the other think it's not going to?" she said.

Ms Main said until the design issues had been nailed down council could only consider a range of operational costs.

"The industries that discharge into the system need to know, so they know what costs they will be faced with."

She said this approach was "completely sensible".

"The peer review is what didn't happen with the first wastewater plant - or, if they did happen, they weren't taken notice of. We can't afford that risk. We can't have a peer reviewer say there are risks and then council do nothing about that.

"I'm comfortable with that design but it's those ongoing costs. And if those costs are unaffordable, then how do we reduce them?" she said.

Advertisement
Advertise with NZME.

The sludge created by the treatment process was the problem in the wastewater treatment plant commissioned only seven years ago.

The council decided an upgrade was essential, with the upgrade tagged at $24 million.

Save

    Share this article

Latest from Whanganui Chronicle

Whanganui Chronicle

RSA 'alive and well' despite premises closure

11 Jul 06:00 PM
Whanganui Chronicle

‘Everyone went silent’: Whanganui Youth MP speaks in Parliament

11 Jul 05:00 PM
Opinion

Shelley Loader: How we can all get a share of the apples

11 Jul 05:00 PM

From early mornings to easy living

sponsored
Advertisement
Advertise with NZME.

Latest from Whanganui Chronicle

RSA 'alive and well' despite premises closure

RSA 'alive and well' despite premises closure

11 Jul 06:00 PM

Former members are 'more than welcome' to return, RSA Welfare Trust president says.

‘Everyone went silent’: Whanganui Youth MP speaks in Parliament

‘Everyone went silent’: Whanganui Youth MP speaks in Parliament

11 Jul 05:00 PM
Shelley Loader: How we can all get a share of the apples

Shelley Loader: How we can all get a share of the apples

11 Jul 05:00 PM
Major Joanna Margaret Paul exhibition opens

Major Joanna Margaret Paul exhibition opens

11 Jul 05:00 PM
Solar bat monitors uncover secrets of Auckland’s night sky
sponsored

Solar bat monitors uncover secrets of Auckland’s night sky

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Whanganui Chronicle e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Whanganui Chronicle
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Whanganui Chronicle
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Bay of Plenty Times
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • NZME Events
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • © Copyright 2025 NZME Publishing Limited
TOP