Northern Advocate
  • Northern Advocate home
  • Latest news
  • Business
  • Opinion
  • Lifestyle
  • Sport
  • Property
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Business
  • Opinion
  • Lifestyle
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology
  • Sport
  • Property
    • All Property
    • Residential property listings

Locations

  • Far North
  • Kaitaia
  • Kaikohe
  • Bay of Islands
  • Whangārei
  • Kaipara
  • Mangawhai
  • Dargaville

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Kaitaia
  • Whangārei
  • Dargaville

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / Northern Advocate

State Highway 1 over Mangamuka Gorge in Far North on course to reopen before Christmas

Mike Dinsdale
By Mike Dinsdale
Editor. Northland Age·Northern Advocate·
31 May, 2024 07:09 AM6 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

One of the 1308 piles sunk into the Mangamuka Gorge repair project on State Highway 1 in the Far North.

One of the 1308 piles sunk into the Mangamuka Gorge repair project on State Highway 1 in the Far North.

The two-year repair job to fully fix State Highway 1 over Mangamuka Gorge in the Far North has been so extensive and complex that an extra $60 million to finish the job was allocated in Thursday’s Budget.

That takes the total cost of the repair – 35 slips over a 13km stretch – to $160m, after an initial $100m was allocated for the work in December 2022. NZ Transport Agency Waka Kotahi says the work is due to be finished and the road ready to fully open before Christmas, if the weather holds up.

An exact opening date should be known in September, but whatever that date is, many people in the Far Far North will celebrate the reopening of one of its lifelines to the world.

The highway was first closed in July 2020 due to a 1-in-500-year weather event where two slips required complex engineering solutions for repair over 11 months.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

The SH1/Mangamuka Gorge situation developed into multiple significant slips and extensive damage caused by severe weather which closed the gorge in August 2022 for the second time in two years.

While the route carries only about 1300 vehicles per day, it is an economic lifeline for the district and a key connector for the Far North to the rest of Northland and New Zealand.

Work is going on around the clock at Mangamuka Gorge, with three shifts used and about 150 workers on site every day.
Work is going on around the clock at Mangamuka Gorge, with three shifts used and about 150 workers on site every day.

Bouts of wet weather through 2023 resulted in more slips within the site area, adding complications to existing slip sites and created an increase in scope that resulted in delays to the initial work programme. The number of slips more than doubled to 35, with 15 defined as critical. The earlier repairs completed during the previous closure in 2021 held up well and were undamaged in the more recent weather events, requiring no additional work to be undertaken in these areas, NZTA senior project manager Hendrik Postma said.

Media were taken to the site on Friday for a visit to show progress on the repair job. It still looks like, and is, a major work site, with trucks frequently back and forth picking up and dumping soil from the repairs.

Advertisement
Advertise with NZME.

Kylie Harris is the comms and engagement manager for the project’s main contractor CLL. She was born and grew up in Kaitāia and is among about 75 per cent of the total workforce on the site – currently almost 150 – who are from the surrounding areas. Her partner, father, uncle and a nephew were among whānau members working on the site.

NZTA Waka Kotahi Mangamuka senior project manager Hendrik Postma on the retaining wall that has been so successful it’s become the new standard for such walls on state highway projects.
NZTA Waka Kotahi Mangamuka senior project manager Hendrik Postma on the retaining wall that has been so successful it’s become the new standard for such walls on state highway projects.

Harris said having a high level of local workers meant they were all invested in the project and determined to ensure it was done as quickly as possible, without damaging the environment and some of the area’s unique flora and fauna.

She said there had been a fish passage to allow precious inanga and tuna to migrate to the nearby wetland, and back to the sea; a system to filter runoff water had been invented and kauri snail/pupurangi were regularly seen crossing the road by the worksite and they had to be looked after.

“My grandfather is a Maheno from Te Pātū [one of the six Muriwhenua iwi] and my mother is from Peria [not far north of Mangamuka] so we have deep connection to the whenua.”

She and the rest of the local workers could not wait for the road to reopen so access to the Far Far North can be fully restored.

Kylie Harris, from main contractor CLL, grew up in Kaitāia and is among about 75 per cent of the total workforce on the site who are locals.
Kylie Harris, from main contractor CLL, grew up in Kaitāia and is among about 75 per cent of the total workforce on the site who are locals.

Another innovation on the site is a retaining wall that has now set the standard for such walls on other Waka Kotahi projects, Postma said.

The wall was constructed after the 2020 slips and he said after the 2022 slips they were surprised to see the wall had help up far better than expected.

“It’s not a cheap fix, but it definitely works and is now being used on other projects because it’s so good.”

A fleet of six trucks each carry up to 7cu m of soil and make up to 23 trips a day on the Mangamuka job.
A fleet of six trucks each carry up to 7cu m of soil and make up to 23 trips a day on the Mangamuka job.

NZTA Waka Kotahi Mangamuka Project Director Mark Ware said the progress comes despite some challenging weather.

“The past year was one of the wettest on record, with over one metre more rainfall than the historical average in the area. Usually the region gets approximately 1700mm of rain in 12 months – in contrast, over the past year there’s been over 2800mm of rain,” Ware said.

Advertisement
Advertise with NZME.

With so much extra rain, contractors have lost 23 full days of possible working time, which also didn’t help.

Another big issue is Northland Problematic Rock. No, it’s not a new musical genre from the region, it’s the main reason SH1 over the Mangamukas keeps slipping and has taken almost four years to fully repair.

The largest of the 35 Mangamuka Gorge slips that is still being repaired. It should be finished in the next few weeks
The largest of the 35 Mangamuka Gorge slips that is still being repaired. It should be finished in the next few weeks

Northland’s ground conditions (including through the Maungataniwha Range which surround Mangamuka Gorge) have always been fragile. Almost 70 per cent of the geological material which forms rocks in the region is made up of Northland Allochthon, better known as “Northland Problematic Rock”.

This type of material has long been challenging for construction and maintenance of roads, and means repairs to slips of this nature need to be carefully planned, since finding competent material to anchor the road to can be difficult, Ware said.

He said some of the 1308 piles had to go down 35m, but due to the ground structure, anchors for some of the piles had to be drilled 32m into the hillside so they could hit solid rock.

REPAIRS BY NUMBERS:

$160 million – total cost of the repair work after an extra $60m was allocated in Thursday’s Budget

Advertisement
Advertise with NZME.

365,000 – hours have been worked on-site since the works started at the end of February 2023

35 – slips over 13km

1.3km – area the slips covered

3 – out of 15 critical slip repairs are now complete, while three more are in the final stages of completion

30,000cu m – of material needs to be removed

1308 – piles sunk into the Mangamuka Gorge repair project

Advertisement
Advertise with NZME.

1300 – vehicles per day normally travel over SH1 Mangamuka Gorge

142 – individuals work on site daily

950 – individuals have been inducted to work on-site since work started

142 – companies involved in the project, 56 per cent are Far North companies, 68 per cent are Northland companies

Contractors work on one of the 35 slips that have closed SH1 over the Mangamuka Gorge.
Contractors work on one of the 35 slips that have closed SH1 over the Mangamuka Gorge.


Kauri snails/pupurangi are a regular sight on SH1 over Mangamuka Gorge during repair works at the site.
Kauri snails/pupurangi are a regular sight on SH1 over Mangamuka Gorge during repair works at the site.
NZTA Waka Kotahi Mangamuka Project Director Mark Ware and senior project manager Hendrik Postma are delighted at the progress work on the Mangamuka Gorge repair work.
NZTA Waka Kotahi Mangamuka Project Director Mark Ware and senior project manager Hendrik Postma are delighted at the progress work on the Mangamuka Gorge repair work.
Save

    Share this article

Latest from Northern Advocate

Northern Advocate

News in brief: Sandbox Fandom Festival 2025 returns to Whangārei in July

17 Jun 05:00 PM
Northern Advocate

'A lot of tears': Concerns over changes to post-mortem examinations

17 Jun 05:00 PM
Northern Advocate

'You and cars are a bad mix': Man who hit oncoming motorist high on dangerous levels of meth

17 Jun 04:00 AM

Jono and Ben brew up a tea-fuelled adventure in Sri Lanka

sponsored
Advertisement
Advertise with NZME.

Latest from Northern Advocate

News in brief: Sandbox Fandom Festival 2025 returns to Whangārei in July

News in brief: Sandbox Fandom Festival 2025 returns to Whangārei in July

17 Jun 05:00 PM

The latest news bites from around the region.

'A lot of tears': Concerns over changes to post-mortem examinations

'A lot of tears': Concerns over changes to post-mortem examinations

17 Jun 05:00 PM
'You and cars are a bad mix': Man who hit oncoming motorist high on dangerous levels of meth

'You and cars are a bad mix': Man who hit oncoming motorist high on dangerous levels of meth

17 Jun 04:00 AM
Koru stolen from community leader's grave back with whānau

Koru stolen from community leader's grave back with whānau

17 Jun 03:10 AM
Help for those helping hardest-hit
sponsored

Help for those helping hardest-hit

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • The Northern Advocate e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Northern Advocate
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • The Northern Advocate
  • The New Zealand Herald
  • The Northland Age
  • Waikato Herald
  • Bay of Plenty Times
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • © Copyright 2025 NZME Publishing Limited
TOP