Bay of Plenty Times
  • Bay of Plenty Times home
  • Latest news
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Sport
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Business
  • Opinion
  • Lifestyle
  • Property
    • All Property
    • Residential property listings
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology
  • Sport

Locations

  • Coromandel & Hauraki
  • Katikati
  • Tauranga
  • Mount Maunganui
  • Pāpāmoa
  • Te Puke
  • Whakatāne
  • Rotorua

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Thames
  • Tauranga
  • Whakatāne
  • Rotorua

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / Bay of Plenty Times

Tauranga pipeline finish slips further behind schedule

John Cousins
By John Cousins
Senior reporter, Bay of Plenty Times·Bay of Plenty Times·
15 Apr, 2018 04:05 AM3 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

Southern Pipeline project manager Steve Wiggill has encountered more problems on the last leg of the $99 million project. Photo/File

Southern Pipeline project manager Steve Wiggill has encountered more problems on the last leg of the $99 million project. Photo/File

Construction of Tauranga's $99 million Southern Pipeline will end up being delayed by nearly another year after the contractor struck more problems trying to drill the pipeline under the bed of the harbour.

The most technically challenging section of the pipeline from Memorial Park to Matapihi Peninsula lived up to its name, with uncertainty around who would carry the cost overruns - the Tauranga City Council or the contractor.

Latest problems involved the discovery of much softer conditions than expected deep under the bed of Tauranga Harbour.

Council project manager Steve Wiggill said the soft material needed to be stabilised so the pipeline ran through firmer conditions. This plus the remaining work left to complete the project was expected to take another seven months.

The $21m harbour crossing had been expected to be finished by December last year. The new timetable put completion out to mid-November this year.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

Wiggill said the project budget was still $99m. It included a contingency - the size of which was commercially sensitive.

''There have been some cost overruns as a result of the delays, but it is yet to be decided who will carry these.''

The contractor planned to firm up the soft material by using harder drilling mud.

Advertisement
Advertise with NZME.

Wiggill said a smaller steel sleeve was being pushed through the 152cm outer steel sleeve driven into the bed of the harbour from the Memorial Park side.

As the smaller sleeve moved through the softer material into deeper, firmer material, a mixture of drilling mud would be injected to harden and stabilise the area of softer material, he said.

The contractor had so far finished more than two-thirds of the under-harbour reaming work to widen the initial 75cm diameter pilot hole drilled under the harbour.

"This has been an extremely challenging project. We've had to overcome several issues, beginning with an obstruction we encountered under the harbour back in August 2017 which badly damaged our machinery and created a domino effect of complications,'' Wiggill said.

Discover more

Council consultation period closes at 4pm today

16 Apr 01:30 AM

Matapihi speed limit dropping to 60km/h

17 Apr 06:00 PM

Southern Pipeline halfway across harbour

23 Jul 06:00 PM
New Zealand

Pipeline emerges under harbour after 8 years

23 Jul 09:45 PM

A panel of global drilling experts had been brought in to find a solution to stabilise the soft material.

Wiggill said the driver for the Southern Pipeline was the protection of the environment and that continued to be the focus.

"We have been working closely with iwi representatives and meeting with residents close to the site to update them on the project. It's been a tough project but the team has overcome each issue they've encountered.''

After the soft material had been stabilised, work would resume to widen the final section of the harbour crossing. That was expected to take up to four weeks. Steel pipes would then be pulled through the harbour crossing, followed by the polyethylene wastewater pipes.

Wiggill said the final phase of this project was to connect the wastewater pipe to the previously constructed pipeline at Matapihi Rd and to the pump station in Memorial Park.


Southern Pipeline Progress
• Original completion target early 2010.
• Laying of pipeline began mid 2010 at Greerton.
• Revised 2017 completion target December 2017.
• Latest completion target mid-November 2018.

Advertisement
Advertise with NZME.
Save

    Share this article

Latest from Bay of Plenty Times

Bay of Plenty Times

Tribesmen's alleged 'hotbox' murder after gang member's unauthorised online shopping

16 Jun 07:30 AM
Bay of Plenty Times

Waihī house fire: Probe into cause of man's death

16 Jun 06:09 AM
Bay of Plenty Times

Bunnings' $53m Tauranga store set to open

16 Jun 03:00 AM

How one volunteer makes people feel seen

sponsored
Advertisement
Advertise with NZME.

Latest from Bay of Plenty Times

Tribesmen's alleged 'hotbox' murder after gang member's unauthorised online shopping

Tribesmen's alleged 'hotbox' murder after gang member's unauthorised online shopping

16 Jun 07:30 AM

Mark Hohua, known as Shark, was allegedly beaten to death by fellow gang members in 2022.

Waihī house fire: Probe into cause of man's death

Waihī house fire: Probe into cause of man's death

16 Jun 06:09 AM
Bunnings' $53m Tauranga store set to open

Bunnings' $53m Tauranga store set to open

16 Jun 03:00 AM
BoP dairy targeted by armed robbers

BoP dairy targeted by armed robbers

16 Jun 01:00 AM
Jono and Ben brew up a tea-fuelled adventure in Sri Lanka
sponsored

Jono and Ben brew up a tea-fuelled adventure in Sri Lanka

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Bay of Plenty Times e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Bay of Plenty Times
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Bay of Plenty Times
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • NZME Events
  • © Copyright 2025 NZME Publishing Limited
TOP