Bay of Plenty Times
  • Bay of Plenty Times home
  • Latest news
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Sport
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Business
  • Opinion
  • Lifestyle
  • Property
    • All Property
    • Residential property listings
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology
  • Sport

Locations

  • Coromandel & Hauraki
  • Katikati
  • Tauranga
  • Mount Maunganui
  • Pāpāmoa
  • Te Puke
  • Whakatāne
  • Rotorua

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Thames
  • Tauranga
  • Whakatāne
  • Rotorua

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In

Advertisement
Advertise with NZME.
Home / Bay of Plenty Times

Tauranga faces huge bill for defective Harington St transport hub carpark building

RNZ
20 Aug, 2020 06:36 AM9 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

Harington St Transport Hub. Photo / File

Harington St Transport Hub. Photo / File

By RNZ

Tauranga ratepayers face a $7 million-plus bill to demolish a defect-riddled central city carpark building but dodged a catastrophic failure.

The structural designer of Harington St Transport Hub, a 550-space carpark building, said it blew the whistle on itself.

But the city council rejects that.

It has launched legal action against the designer and "others" it has not named, and lodged official complaints asking for action against three engineers.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

It has been advised the best option is to limit losses to about $27m all-up by pulling down the Harington St Transport Hub block, versus spending $65m rebuilding it, according to documents newly released to RNZ.

However, council infrastructure manager Nic Johansson sweats an even worse outcome.

"Someone might have had the attitude that 'she'll be right' and carried on," he said.

Advertisement
Advertise with NZME.

"We could have ended up with a completed building that would have worked and looked quite fine until there was a seismic event, and it could have been a catastrophic outcome."

The documents show a litany of floor, column and bracing weaknesses that have deterred the council - and contractors - from wanting to even try to remediate the building.

They include foundations so thin they needed another 300 tonnes of reinforcing steel and 140 truckloads of concrete, eight columns that needed destroying using hydro jets, to rebuild, while propping up floors above, welds missing between plates and ungraded steel in key brace connections.

Construction has stopped on Tauranga's Harington St Transport Hub.  Photo / File
Construction has stopped on Tauranga's Harington St Transport Hub. Photo / File

A multi-storey build unravels

The carpark building, commissioned at $29m to boost the city centre, was already 20m out of the ground in March 2019, when a concrete pour went ahead - and a beam twisted.

Discover more

'Dreadfully dull': Fears for CBD's vitality after Transport Hub dumped

22 Jun 06:12 PM

Letters to the editor: Chronicles of the Harington St 'Transport Hub'

19 Jun 03:00 PM

Letters to the editor: Minister's marine reserve decision a sad one

30 Jul 09:00 PM

New time limits for city centre on-street parking

04 Aug 02:01 AM

The whole project then began to unravel.

At that stage, "two-thirds of the structural steel had been erected and half of the concrete elements completed", the documents said.

"Whilst not expressly stated at the time, it became apparent that the issue related to the seismic resilience of the building."

That took months to come to light - initially, the council believed the defects were few and isolated.

The building's designer, veteran nationwide structural engineering company Harrison Grierson, did a review, told the council there was "an issue with the ramps", made some localised design changes, and the council issued another consent in July 2019.

Harrison Grierson's managing director Glen Cornelius claimed to RNZ that his firm blew the whistle on itself.

Advertisement
Advertise with NZME.

"It was Harrison Grierson who identified and advised the council that a remedial design was needed for the building," Cornelius said in a statement.

Johansson was non-plussed at that claim.

"I struggle to understand that statement," he said.

It was the builder, Watts and Hughes, that raised the alarm and responded well, he said, leading to what proved to be a vital decision by the council to call in outside assessors, at the same time as Harrison Grierson was amending its original design.

"We were starting to lose confidence," Johansson said.

"We had specialists on site and it became obvious there weren't seismic [proof] joints between the ramps and the floor slabs.

Advertisement
Advertise with NZME.

"There were real doubts about the design principles and the fundamentals."

As for Harrison Grierson, "it was only in August that it was recognised by them" just how big the problems were, he said.

Complaints against engineers

A full halt to construction was called in September 2019.

Costs to the council carried on, at $4000 per day - not accounting for the loss to Tauranga of extra carparking.

By then it was clear that parts of the site, like the stairwells, were not safe to work around, though seismic forces were not in play in the same threatening way as they would be were the building actually finished with its full loading on the walls, Johansson said.

The council has now lodged official complaints asking Engineering New Zealand to take action against the two original designers.

Advertisement
Advertise with NZME.

The council said those two had since left Harrison Grierson.

It has lodged a third complaint against the engineer who approved the design in an independent peer review done at a small engineering company, Constructure.

Constructure founder Cory Bedford, of Christchuch, would not go on tape but told RNZ "the peer review Constructure undertook is a public issue and Constructure is responsible for that".

They were in discussions with the council, Bedford said, adding "I'm not comfortable on stating anything further to you", and referring RNZ to his lawyer.

Constructure's website says it has completed 11,000 projects in 12 years, 9000 of those in Canterbury - and 10 award-winning; in 2015 it had 18 staff, and now has 26.

Both Constructure, and Harrison Grierson said they had undertaken internal reviews of what went wrong but rejected the need for independent review.

Advertisement
Advertise with NZME.

"Our internal review was undertaken by senior Harrison Grierson personnel who were not involved directly with the Harington St Transport Hub project to ensure their objectivity," Cornelius said.

"The review considered where the issues were, how they came about and what Harrison Grierson can do to ensure this doesn't happen again."

The problems were confined to the carpark, and did "not reflect the depth of expertise and standard of service we set ourselves", Cornelius said.

Harrison Grierson employs several hundred people and has been in business 130 years.

 Tauranga's Harington St Transport Hub pictured in November 2019.  Photo / File
Tauranga's Harington St Transport Hub pictured in November 2019. Photo / File

'Hate for anyone else' to go through this

The council abandoned the project formally two months ago.

It was "tortuous" getting to that point, Johansson said.

Advertisement
Advertise with NZME.

In late 2019, the council thought coming up with a remedial design that would result in a good-enough building was do-able.

By early 2020, that had begun to slip away, the documents show.

Watts and Hughes, and major engineering firm, Aurecon, could not agree with Harrison Grierson on a strengthening plan.

By May, the seismic bracing system was still not figured out.

"As part of the column strengthening, steel plates are required which pass through the existing completed concrete slabs," one advisory report said.

The steelwork subcontractor didn't think the strengthened design, unfinished as it was, was even buildable.

Advertisement
Advertise with NZME.

"Removing and replacing a ramp that is tied to the basement floor requires considerable demolition and planning to complete safely," Watts and Hughes told the council.

"Both basement wall strengthening, ramp removal and replacement see large steel beams and columns being removed and re-fitted.

"The waterproofing of fixings through the exterior precast walls poses risk and no guarantee has been given or obtained for these works based on the design."

The durability of the carpark was not even looked into, Aurecon said in June.

Demolition was very likely, the council told RNZ.

Its advice was that if it rebuilt or strengthened the block, then hiked carparking rates to try to recover costs, this would be a bad option, especially with Covid disrupting carparking demand, the documents show.

Advertisement
Advertise with NZME.

A rebuild would be so noisy - and dusty - it would probably break council noise control rules.

Harington St Transport Hub.  Photo  /  File
Harington St Transport Hub. Photo / File

"I hope everyone that is involved in the sector sits up and takes notice," Johansson said.

"I would hate for anyone else to end up with a ... $27m dollar hole."

Can't 'check the checker'

Construction monitoring at the carpark building did not pick up the design faults early on.

Also, the council did not spot them when it consented the flawed design.

But there was a limit to what checks could be done, Johansson said. Hiring a "checker to check the checker" was not how the system worked, and it would be better if the industry simply lifted its game.

Advertisement
Advertise with NZME.

"The council has every right to rely on the engineering expertise from those designers that have got the right qualifications and quality marks around it," he said.

"Councils simply don't hold the expertise of going into the degree of check," it would require to review engineering designs in-depth.

Public confidence in the council's building department was badly shaken by the debacle of the Bella Vista subdivision three years ago, where consenting failures doomed 21 homes. However, this was entirely different from Harington St, Johansson said.

OIA documents released to RNZ showed the city council's building control team passed its latest accreditation test from the Ministry of Business, Innovation and Employment in September 2019, without any "serious" faults being found.

However, twice as many "moderate" faults - 26 - were found than at its previous assessment.

It was told to fix these by early 2020, MBIE records showed.

Advertisement
Advertise with NZME.

The building team had 11 unfilled technical jobs, about a quarter of its complement.

The bills from trying to rescue the afflicted carpark continue to mount; the documents show about $2m is set aside in case any construction is needed at it this year.

The council might consider compensating neighbouring apartment owners who've had to put up with it.

"It's an incredibly time-consuming and costly problem, and also frustrating to us as an organisation and our community, because now we have an eyesore sitting there much longer than it should be," Johansson said.

"It should have been a functional building being a great asset and amenity for the community."

Someone could still buy the site as-is, and negotiations and legal action could claw back costs, Johansson said.

Advertisement
Advertise with NZME.

RNZ asked if the council was checking other designs. It said another project, a small retaining wall designed by an engineer who worked on the carpark design, was being checked for compliance.

However, it is not reviewing the whole Harington St debacle.

Timeline:
July 2018: Building consent granted

March 2019: Beam twists, triggering alarm

June-July 2019: Seismic design problems revealed

September 2019: Work stops

Advertisement
Advertise with NZME.

Late 2019: Work on remedial strengthening design begins

May 2020: Failure to come up with a strengthening design

June 2020 : Council abandons project

August 2020: Advice to demolish being considered

Save

    Share this article

Latest from Bay of Plenty Times

Bay of Plenty Times

Red and black: How Whaka plans to seize rugby glory

Bay of Plenty Times

Rural community 'in shock' as industrial park greenlit

Premium
Bay of Plenty Times

'Stay on your side of the Bombays': Rotorua developer's swipe at Auckland firms


Sponsored

Solar bat monitors uncover secrets of Auckland’s night sky

Advertisement
Advertise with NZME.

Latest from Bay of Plenty Times

Red and black: How Whaka plans to seize rugby glory
Bay of Plenty Times

Red and black: How Whaka plans to seize rugby glory

Whakarewarewa faces Tauranga Sports in the Baywide Premier Men’s final on Saturday.

17 Jul 12:12 AM
Rural community 'in shock' as industrial park greenlit
Bay of Plenty Times

Rural community 'in shock' as industrial park greenlit

16 Jul 09:04 PM
Premium
Premium
'Stay on your side of the Bombays': Rotorua developer's swipe at Auckland firms
Bay of Plenty Times

'Stay on your side of the Bombays': Rotorua developer's swipe at Auckland firms

16 Jul 09:03 PM


Solar bat monitors uncover secrets of Auckland’s night sky
Sponsored

Solar bat monitors uncover secrets of Auckland’s night sky

06 Jul 09:47 PM
NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Bay of Plenty Times e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Bay of Plenty Times
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Bay of Plenty Times
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • NZME Events
  • © Copyright 2025 NZME Publishing Limited
TOP