"During the geotechnical process, Emmetts Civil Construction investigated the ground conditions and determined additional work is required to strengthen the design," Leitao said.
Engineers may need to change the materials used, the pile depth and the bank stabilisation. The bridge is being redesigned by Emmetts with the help of Holmes Consulting, and is now not due to be finished until April next year.
Emmetts is also to build the cycle path to the town limit, with earthwork done by B Bullock. That's to start in September, Leitao said.
The path will run close to Papaiti Rd, along the riverbank, and no other bridges will be needed.
Whanganui & Partners destination marketing strategic lead Paul Chaplow said the bridge will grow Whanganui's cycling culture.
"The bridge will be a real asset to Whanganui, not only because it improves the Mountains to Sea cycle route but because it creates more cycling options with an easily accessible, flat, cycle-friendly day ride to Upokongaro."