Northern Advocate
  • Northern Advocate home
  • Latest news
  • Business
  • Opinion
  • Lifestyle
  • Sport
  • Property
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Business
  • Opinion
  • Lifestyle
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology
  • Sport
  • Property
    • All Property
    • Residential property listings

Locations

  • Far North
  • Kaitaia
  • Kaikohe
  • Bay of Islands
  • Whangārei
  • Kaipara
  • Mangawhai
  • Dargaville

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Kaitaia
  • Whangārei
  • Dargaville

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / Northern Advocate

Kerikeri residents lose faith after wastewater plant delays

Susan Botting
By Susan Botting
Local Democracy Reporter·Northern Advocate·
1 Jul, 2020 11:00 PM3 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

One of 70 pre-cast concrete panels for Kerikeri's new wastewater treatment plant last year. Photo / FNDC

One of 70 pre-cast concrete panels for Kerikeri's new wastewater treatment plant last year. Photo / FNDC

Angry Kerikeri residents say they have no faith their town's new $27 million wastewater treatment plant will be working by January.

"We were told by Far North District Council we would have reticulated sewerage to our properties by the end of 2017," Jane Johnston, Kerikeri Residents and Ratepayers Association president, said.

There had been ongoing updates on that since then, none of which had happened, Johnston said.

"There have been ongoing delays that are affecting the Kerikeri economy."

In August last year, the Northern Advocate reported the plant was to have been completed by December 2019. By December, FNDC said the plant was to be completed in April 2020.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

Its latest forecast now has the plant due to be finished by the end of September.

The Northern Advocate also reported in the same article that Kerikeri households and businesses were expected to be able to connect to the scheme by July this year.

By December last year, FNDC said this would happen in September this year, but January next year is now the latest forecast.

Advertisement
Advertise with NZME.

The plant's project delivery performance was part of an update in FNDC chief executive Shaun Davidson's report to the council's meeting last Thursday.

This showed the plant red-carded on all five project plan performance target indicators. It failed to achieve across all targets, including project completion status, the scope for the project growing, its rates of progress and costs tracking.

Andy Finch, FNDC general manager infrastructure and asset management, said performance on those indicators was not unexpected for a project of the plant's size.

The indicators and their milestones had been set up at the start of the project. There had been a lot of changes since.

Discover more

First peek at $4.5m, 22-metre fishing vessel

28 Jun 11:00 PM

Far North kauri sanctuary, Māori tourism projects get $7.5m funding boost

28 Jun 06:00 PM

Dog attack on national icon: Five kiwi dead

29 Jun 05:00 PM

Far North gets 3km of new footpaths

03 Jul 01:00 AM

Indicators presented to the meeting showed a "fairly pessimistic" view of what would be a successful project.

"I don't think this metric does it any justice," Finch told councillors.

The report said the scope of the project had expanded due to design issues because the contract had been let without "issued for construction" drawings. These are detailed design drawings integral to assessing exactly what work is to be involved in a contract.

There were also significant impacts on the project's completion schedule, from addressing health and safety compliance issues identified through project risk assessment.

Johnston said delays had meant continued trucking of some of Kerikeri's sewage to Kaikohe for processing.

They had potentially impacted on the area's water quality as people held off upgrading septic tanks in expectation of being able to go onto a reticulated wastewater system.

Advertisement
Advertise with NZME.

Development was affected, sometimes illogically, Johnston said. Residential subdivisions in the new areas to be brought into the scheme could not go ahead while those in areas outside the scheme could.

FNDC said the new plant would triple the amount of wastewater treated by the town's existing Shepherd Rd plant. In December last year, it said this plant was due to be shut down in October.

The council said the new scheme would serve all properties already connected to Kerikeri's wastewater system plus 350 new properties on septic tanks.

It will also have the capacity to serve 400 further properties and is designed for expansion to provide for further growth.

Save

    Share this article

Latest from Northern Advocate

Northern Advocate

Three bidders confirmed for Northland Expressway PPP

21 Jun 05:00 PM
Northern Advocate

'I wouldn't wish it on anyone': Why are victims having to wait until 2027 for justice?

21 Jun 01:00 AM
Premium
Opinion

Opinion: Endless tourist tours are our modern purgatory

20 Jun 05:00 PM

Jono and Ben brew up a tea-fuelled adventure in Sri Lanka

sponsored
Advertisement
Advertise with NZME.

Latest from Northern Advocate

Three bidders confirmed for Northland Expressway PPP

Three bidders confirmed for Northland Expressway PPP

21 Jun 05:00 PM

Initial construction work on the next section is set to begin by the end of next year.

'I wouldn't wish it on anyone': Why are victims having to wait until 2027 for justice?

'I wouldn't wish it on anyone': Why are victims having to wait until 2027 for justice?

21 Jun 01:00 AM
Premium
Opinion: Endless tourist tours are our modern purgatory

Opinion: Endless tourist tours are our modern purgatory

20 Jun 05:00 PM
Why kiwi deaths on roads highlight a conservation success story

Why kiwi deaths on roads highlight a conservation success story

20 Jun 02:00 AM
Help for those helping hardest-hit
sponsored

Help for those helping hardest-hit

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • The Northern Advocate e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Northern Advocate
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • The Northern Advocate
  • The New Zealand Herald
  • The Northland Age
  • Waikato Herald
  • Bay of Plenty Times
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • © Copyright 2025 NZME Publishing Limited
TOP