“Poor weather and colder than expected temperatures have delayed the programme slightly, meaning the work programme is expected to be complete in early October.”
Mr Taylor said an estimated 80,000 square metres of asphalt will be laid by the end of the programme.
“This stretch of road is a crucial lifeline for the community. These closures enable us to strengthen this stretch of SH2 safely and efficiently, and we appreciate people’s patience and support while we do this.”