Bay of Plenty Times
  • Bay of Plenty Times home
  • Latest news
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Sport
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Business
  • Opinion
  • Lifestyle
  • Property
    • All Property
    • Residential property listings
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology
  • Sport

Locations

  • Coromandel & Hauraki
  • Katikati
  • Tauranga
  • Mount Maunganui
  • Pāpāmoa
  • Te Puke
  • Whakatāne
  • Rotorua

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Thames
  • Tauranga
  • Whakatāne
  • Rotorua

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / Bay of Plenty Times

Transport Minister and contractor give SH25A update as site is prepared for new viaduct bridge

Jim Birchall
By Jim Birchall
Former editor - HC Post·Hauraki Coromandel Post·
18 Aug, 2023 06:24 AM3 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

An artist's impression of the new bridge reconnecting SH25A in the Coromandel. The project is expected to be finished by March. Photo / Waka Kotahi

An artist's impression of the new bridge reconnecting SH25A in the Coromandel. The project is expected to be finished by March. Photo / Waka Kotahi

Minister for Transport and the Environment David Parker was joined at the SH25A Taparahi Bridge Construction site on Friday by Workplace Relations and Safety Minister Carmel Sepuloni, Thames Coromandel District Council (TCDC) Mayor Len Salt and Coromandel MP Scott Simpson to provide an update on the project that aims to reconnect the highway to major tourist hubs.

After heavy rains created cracks on the highway on 15 January this year, further inclement weather from the Auckland Anniversary Weekend rainfall event on 27 January caused the road to be closed, before it gave way sweeping away a 60-metre section of the road.

Damage from Cyclones Hale and Gabrielle, aggrandized the gap to about 110 metres, and the destruction cut off access to the eastern Coromandel Peninsula at the summit of State Highway 25A at Taparahi, around 10km from Kopu south of Thames.

In May, former Transport Minister Michael Wood announced Waka Kotahi NZ Transport Agency’s preferred option was to replace the missing section with a bridge, saying it would be the” the fastest, most resilient way forward.”

Rebuild costs were estimated to cost $30-40 million, with completion set for early 2024.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.
Coromandel MP Scott Simpson, Workplace Relations and Safety Minister Carmel Sepuloni, Hugh Milliken, Project Director MᶜConnell Dowell and Thames Coromandel District Mayor Len Salt at the SH25A Taparahi rebuild site.
Coromandel MP Scott Simpson, Workplace Relations and Safety Minister Carmel Sepuloni, Hugh Milliken, Project Director MᶜConnell Dowell and Thames Coromandel District Mayor Len Salt at the SH25A Taparahi rebuild site.

David Parker reaffirmed today the project was on track for a March 2024 completion, but said the cost would come within the “50 million target” which, if accurate, is a blowout of at least $10 million from the originally quoted figure.

“This is an enormous project and they (the contractors McConnell Dowell) are going to deliver it by March next year. They’ve really rattled their daggs to get this under way, and I’m impressed how they are delivering this so quickly using existing designs and bringing materials from around the country. They’ve got people working 24 hours a day assembling the girders that go on top of the piles and (holes for) abutment piles on the other side have been drilled, " Parker said.

Piles have been installed in anticipation of a new bridge at Taparahi on SH25A.
Piles have been installed in anticipation of a new bridge at Taparahi on SH25A.

Mayor Len Salt spoke of the enormity of the job: “I was up here shortly after this slip happened and the scale was absolutely incredible, and to see the project under way is really good for our community.”

Advertisement
Advertise with NZME.

Salt praised the Government and Waka Kotahi for “getting things moving to this stage,” and added that council was “looking forward to getting this done and open again.”

McConnell Dowell’s Hugh Milliken, the site’s project director, gave updates on the work undertaken at the site by up to 50 contractors, a number expected to rise to around 100 personnel who will work over a 24-hour cycle in the coming weeks.

Milliken said that currently “there is a lot of site stabilisation going on” to prepare the area was the bridge’s installation and noted that off-site fabrication of the bridge was under way.

He intimated time is of the essence:

“We are effectively in a race to prepare the site to take heavy equipment to actually assemble the bridge. We have piling works under way which are fundamental to support the bridge.”

The piles are at a depth of around 35 metres, and Milliken spoke of the challenges of building on an area based on top of modified soft rock comprised of eroded material loosened by recent deluges adding to material from the road’s original construction in the 1970s.

“The site still has all of that modified stuff on top of it, and what we know now is when this was built, it was built using fill - most of that was modified. They pushed it in here, compacted it and a road was built under it and it survived 50 years.”

Save

    Share this article

Latest from Bay of Plenty Times

Bay of Plenty Times

'The man I once trusted violently raped me': Man jailed for attacking ex-wife next to sleeping child

07 Jul 08:00 AM
Bay of Plenty Times

'Do it now, run him over'. Teen who ran over mother's partner twice can finally be named

07 Jul 07:00 AM
Bay of Plenty Times

Hunter who feeds the hungry named Volunteer of the Year

07 Jul 06:56 AM

From early mornings to easy living

sponsored
Advertisement
Advertise with NZME.

Latest from Bay of Plenty Times

'The man I once trusted violently raped me': Man jailed for attacking ex-wife next to sleeping child

'The man I once trusted violently raped me': Man jailed for attacking ex-wife next to sleeping child

07 Jul 08:00 AM

The man apologised to his victim, but pleaded not guilty.

'Do it now, run him over'. Teen who ran over mother's partner twice can finally be named

'Do it now, run him over'. Teen who ran over mother's partner twice can finally be named

07 Jul 07:00 AM
Hunter who feeds the hungry named Volunteer of the Year

Hunter who feeds the hungry named Volunteer of the Year

07 Jul 06:56 AM
Downhill mountain bikers impress on world stage

Downhill mountain bikers impress on world stage

07 Jul 06:38 AM
Solar bat monitors uncover secrets of Auckland’s night sky
sponsored

Solar bat monitors uncover secrets of Auckland’s night sky

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Bay of Plenty Times e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Bay of Plenty Times
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Bay of Plenty Times
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • NZME Events
  • © Copyright 2025 NZME Publishing Limited
TOP