Bay of Plenty Times
  • Bay of Plenty Times home
  • Latest news
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Sport
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Business
  • Opinion
  • Lifestyle
  • Property
    • All Property
    • Residential property listings
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology
  • Sport

Locations

  • Coromandel & Hauraki
  • Katikati
  • Tauranga
  • Mount Maunganui
  • Pāpāmoa
  • Te Puke
  • Whakatāne
  • Rotorua

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Thames
  • Tauranga
  • Whakatāne
  • Rotorua

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In

Advertisement
Advertise with NZME.
Home / Bay of Plenty Times

Coromandel’s SH25a bridge taking shape

Hauraki Coromandel Post
24 Oct, 2023 07:12 PM3 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

The first stage of bridge deck construction has started over the slip on SH25A in Coromandel. Video / Waka Kotahi NZ Transport Agency

The final girder has been lifted into place as construction continues on State Highway 25A’s new bridge.

Waka Kotahi said the beam was lifted into place on Wednesday, October 18 – just 10 days after the first was installed. There were three steel girders per span and these were formed from 15 sections in total bolted together.

The next challenge for the team was forming the deck surface with 138 pre-cast reinforced concrete deck slabs and installing 44 precast side barriers.

To get this into scale these slabs, and the concrete poured in between them, would weigh over 1000 tonnes. The barriers would be placed over these and a levelling and asphalt layer would be laid.

In total, the steel girders would support 1560 tonnes of concrete and asphalt before traffic went over the bridge. This huge load (and the weight of the girders themselves) made the girders bend and to avoid a roller coaster effect as you drive over the bridge the girders were built with a slight arch profile. This was carefully worked out by the designers and carefully built in by the fabricators, Waka Kotahi said.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

As work progressed the girders were monitored to see how well the arch was flattened out by deflection. “Sometimes for lots of reasons it isn’t perfect and fixing takes time. So far – and it’s early days - we are seeing what is expected.”

The construction of the abutments has been completed.
The construction of the abutments has been completed.

Another achievement was the completion of the construction of the abutments, with the team pouring concrete for the wing walls, shown above, for both last Wednesday and Thursday.

With the girders now in place, the team would install the bearings at the abutments and complete the final tensioning of the stress bars which locked the steel girders down on to the pier headstocks.

Advertisement
Advertise with NZME.

The slip stabilisation continued with soil nailing progressing on the eastern slip. To access the slip face, the team were using a mancage-mounted drill rig. Once the soil nails were drilled and grouted, the team would install the mesh over the slip face.

The team had also started the earthworks on the eastern approach, flattening the banks and creating space for drainage channels and side barriers.

Other work in the area

Slip on the Tapu-Coroglen road.  Photo / Supplied
Slip on the Tapu-Coroglen road. Photo / Supplied

With multiple recovery worksites across the peninsula, Waka Kotahi said it was carefully planning the timing and sequencing of the works, to ensure it minimises disruption to traffic over the coming summer months.

Coroglen underslip works continue with rock infill now at road level. Next week contractors will focus on tree removal and clean-up works at the base of the slip. Work would also start next week at the Ruamahunga slip site.

Contractors were also working to complete all recovery activity on SH25A ahead of its opening. This included12 culvert upgrades on the western sides and three on the eastern side and works to clear and upgrade side drains.

Stay up to date with HC Post and Waikato Herald

Get the latest Waikato headlines straight to your inbox Monday to Saturday. Register for free today - click here and choose Local News.

Save

    Share this article

Latest from Bay of Plenty Times

Bay of Plenty Times

Fire crews rescue driver from car that hit building

Bay of Plenty Times

Speedway secures Baypark lease extension to 2039

Bay of Plenty Times

Underslip reduces highway to one lane in BoP


Sponsored

Solar bat monitors uncover secrets of Auckland’s night sky

Advertisement
Advertise with NZME.

Latest from Bay of Plenty Times

Fire crews rescue driver from car that hit building
Bay of Plenty Times

Fire crews rescue driver from car that hit building

One person was rescued and is now with St John.

18 Jul 03:21 AM
Speedway secures Baypark lease extension to 2039
Bay of Plenty Times

Speedway secures Baypark lease extension to 2039

18 Jul 03:00 AM
Underslip reduces highway to one lane in BoP
Bay of Plenty Times

Underslip reduces highway to one lane in BoP

18 Jul 12:51 AM


Solar bat monitors uncover secrets of Auckland’s night sky
Sponsored

Solar bat monitors uncover secrets of Auckland’s night sky

06 Jul 09:47 PM
NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Bay of Plenty Times e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Bay of Plenty Times
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Bay of Plenty Times
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Rotorua Daily Post
  • Hawke's Bay Today
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • NZME Events
  • © Copyright 2025 NZME Publishing Limited
TOP