The Far North District Council has released its decision on accessing land that is required for a water pipeline to supply Kaitaia from a bore at Sweetwater, using compulsory acquisition if necessary.
The decision, made at an extraordinary meeting on December, was released on Wednesday, with a statement saying thecouncil had investigated options to provide Kaitaia with a more resilient water supply for a number of years, and two separate reports had identified the Sweetwater bore as the most viable source. The bore was on privately-owned land, but a subdivision and separate titles had been agreed, and transfer to council ownership was in its final stages.
A 13.5km pipeline was to be laid to connect the bore to the Kaitaia treatment plant. Easements were required for the security and maintenance of that pipeline, and agreement in principle had been reached with all land owners except one, Elbury Holdings Ltd. Final agreement with the other affected land owners was contingent upon the final route through the Elbury Holdings Ltd property.
Councillors had reviewed several different route options, the one chosen representing the best value for the ratepayer in that it was the shortest, while aligning with fences and boundaries identified by Elbury Holdings.
The council clearly believed, however, that the time for negotiating was over, the statement noting that Section 181 of Schedule 12 of the Local Government Act gave councils powers to construct or undertake works on private land without the land owner's consent.
"This is an extraordinary power that needs to be exercised with caution, after all reasonable endeavours to negotiate in good faith have been exhausted or matters of public health and safety are such that prolonged and frustrated negotiations are proving to be barriers to enable the delivery of urgently required public infrastructure works," it added.
"While the council is sympathetic to Elbury Holdings Ltd's situation, ultimately it considered the correct legal processes had been followed, and that as a critical public safety investment project, the Kaitaia Water Project cannot be further delayed. The council accepts the works are required, and are to proceed."
Elbury Holdings Ltd had 14 days from the date of the decision to lodge an appeal in the District Court, whose decision would be final and binding. No further appeals would be available.